 October 2022  New Orleans Investment Conference     Corporate Update Plans for 2022-2024   Exhibit 99.1 
 

 FORWARD LOOKING STATEMENT  The Feasibility Study (“FS”) referenced herein that relates to Peak Gold, LLC (“Peak Gold”), was prepared by Kinross Gold Corporation (“Kinross”), which controls the Manager of Peak Gold and holds 70% of its outstanding membership interests, in accordance with Canadian National Instrument 43-101 (NI 43-101). CORE owns the remaining 30% membership interest in Peak Gold, and must rely on Kinross and its affiliates for the FS and related information. Further, CORE is not subject to regulation by Canadian regulatory authorities and no Canadian regulatory authority has reviewed the FS or passed upon its accuracy or compliance with NI43-101. The terms “mineral resource”, “measured mineral resource”, “indicated mineral resource” and “inferred mineral resource” as used in the resource estimate, the FS and this presentation are Canadian mining terms as defined in accordance with NI 43-101. Mining disclosure in the United States was previously required to comply with SEC Industry Guide 7 (“SEC Industry Guide 7”) under the United States Securities Exchange Act of 1934, as amended. The U.S. Securities and Exchange Commission (the “SEC”) adopted final rules to replace SEC Industry Guide 7 with new mining disclosure rules under sub-part 1300 of Regulation S-K of the U.S. Securities Act (“Regulation S-K 1300”) which became mandatory for U.S. reporting companies beginning with the first fiscal year commencing on or after January 1, 2021. Under Regulation S-K 1300, the SEC now recognizes estimates of “Measured Mineral Resources”, “Indicated Mineral Resources” and “Inferred Mineral Resources”. In addition, the SEC has amended its definitions of “Proven Mineral Reserves” and “Probable Mineral Reserves” to be substantially similar to international standards. CORE is in the process of preparing a Regulation S-K 1300 compliant feasibility study.  Investors are cautioned that while the above terms are “substantially similar” to the NI 43-101 definitions, there are differences in the definitions under Regulation S-K 1300 and NI 43-101. Accordingly, there is no assurance any mineral reserves or mineral resources that CORE may report as “probable mineral reserves”, “measured mineral resources”, “indicated mineral resources” and “inferred mineral resources” under NI 43-101 would be the same had CORE prepared the mineral reserve or mineral resource estimates under the standards adopted under Regulation S-K 1300. U.S. investors are also cautioned that while the SEC recognizes “measured mineral resources”, “indicated mineral resources” and “inferred mineral resources” under Regulation S-K 1300, investors should not assume that any part or all of the mineralization in these categories will ever be converted into a higher category of mineral resources or into mineral reserves. Mineralization described using these terms has a greater degree of uncertainty as to its existence and feasibility than mineralization that has been characterized as reserves. Accordingly, investors are cautioned not to assume that any measured mineral resources, indicated mineral resources or inferred mineral resources that CORE's reports are or will be economically or legally mineable. Please see the CORE's press release dated July 28, 2022 and Kinross' press release dated July 26, 2022 for more detail regarding the FS.  2 
 

 The Preliminary Economic Assessment (“PEA”) referenced herein was prepared in accordance with Canadian National Instrument 43-101 (NI 43-101). CORE is not subject to regulation by Canadian regulatory authorities and no Canadian regulatory authority has reviewed the PEA or passed upon its accuracy or compliance with NI43-101. The terms “mineral resource”, “measured mineral resource”, “indicated mineral resource” and “inferred mineral resource” as used in the resource estimate, the PEA and this presentation are Canadian mining terms as defined in accordance with NI 43-101; however, these terms are not defined terms under the U.S. Securities and Exchange Commission’s (“SEC’s”) Industry Guide 7 and are normally not permitted to be used in reports and registration statements filed with the SEC. The estimation of measured resources and indicated resources involves greater uncertainty as to their existence and the legal and economic feasibility of extraction than the estimation of proven and probable reserves. Conversion of mineral resources to proven and probable mineral reserves generally requires a further economic study, such as a preliminary feasibility study. The PEA is not a preliminary feasibility study and does not support an estimate of proven and probable mineral reserves. Investors are cautioned not to assume that all or any part of an inferred mineral resource exists or is economically or legally mineable. Investors are also cautioned not to assume that all or any part of measured or indicated resources will ever be converted into mineral reserves. In addition, the SEC normally only permits issuers to report mineralization that does not constitute mineral reserves as in-place tonnage of mineralized material and grade without reference to unit amounts of metal. Please see the Company’s press release dated September 24, 2018 for more detail regarding the PEA.  3  CAUTIONARY NOTE REGARDING ESTIMATES OF MEASURED, INDICATED AND INFERRED RESOURCES 
 

 Developing Alaska’s Next Gold Mines  Manh Choh – Development Stage Project under construction in partnership with Kinross (70%) and the Alaska Native Tetlin Tribe (Royalty)  100% Owned Lucky Shot Mine – Exploring historic high-grade gold mine  Three Early-Stage Exploration Projects:  Shamrock  Eagle-Hona  Triple Z  4 
 

 Manh Choh   Gold Deposit  1.3 Million ounce gold Measured plus Indicated Resources1  Average grade = 4g/t Gold1  Located in Alaska on the Alaska Hwy  On Private Land Owned by the Tetlin Alaska Native Tribe  Business Partnership with Kinross – Paid $93 Million for 70% interest  Using the Fort Knox Milling Facilities  Lower capital costs, Smaller Environmental footprint and Lower Execution Risk  1 Based on 100% of the resource reported in the SK1300 Report filed   April 8, 2021 Corporate press release  https://www.sec.gov/Archives/edgar/data/1502377/000115752321001257/a52515098ex96_1.htm  5 
 

 NEAR-TERM PRODUCTION POTENTIAL & EXPLORATION UPSIDE   6  MANH CHOH GOLD PROJECT   NYSE-A:CTGO  September 2020 entered into JV agreement between Contango (30%) and Kinross (70% and Operator) to form new Peak Gold LLC, with Royal Gold and Tetlin Tribe retaining royalty interests;  Plan is to mine Manh Choh Gold ore and then truck and process the ore at Kinross’ Fort Knox Milling Complex  Simple Development Plan - reduces execution risk to produce Gold and Silver over 4.5 year mine-life starting 2024  Projected Timeline: $19 Million 2021 PGLLC Budget  Studies and Permitting in 2021-22  $25.6 million PGLLC Budget Approved for 2022  Recently Amended to $39.6 million  Feasibility in 2022  Construction in 2022/2023  Production in 2024  Explore 2800 sq.km area  
 

 MANH CHOH GOLD PROJECT: Anticipated Economics  Using existing infrastructure at Fort Knox, Peak Gold LLC is planning on a 2024 start date  Kinross estimates 914,000 GEO production over a 4.5-years equating to roughly 225,000 GEO per annum (30% to Contango Ore = 67,500 GEO/Yr)1  Using elevated cut-off grade - Average processed grades expected to be ~8 g/t Au   Capital Costs - Existing infrastructure expected to reduce start-up capital requirements     $182 million (including $21M Contingency) based on Q2 2022 Feasibility Study1   Manager has recommended an additional contingency of $18 million to cover potential inflationary pressures – Contango’s Share  $60 million  Operating Costs - Kinross estimates AISC of ~US$900/GEO1 Contango AISC pending analysis     7  Model Assumptions: per Kinross Disclosure1  1 Based on Kinross Gold Corporation “Q2 Corporate Update ” presentation dated July 27, 2022; Initial capex reflects the feasibility study completed in 2022; The optimization for the mineral reserve estimate assumed a $1,300 per ounce gold price; the $182 Million estimate reflects remaining funds to be expended between 2022 and 2024; there will be additional capital required at Fort Knox to accommodate Manh Choh ore; and there will be a Toll Milling charge to the Peak Gold JV; "All-in sustaining cost (AISC) per equivalent ounce sold“ is a non-GAAP ratio. see Appendix for disclaimers regarding reconciliation. “GEO” refers to Gold Equivalent Ounces. 
 

 The project is located 29 km (18 mi) from the Alaska Hwy and 400 km (240 mi) to the Fort Knox Milling Complex  8  MANH CHOH   GOLD PROJECT LOCATION  MANH CHOH DEPOSIT  Image used with permission from Kinross  Manh Choh 
 

 PEAK GOLD JV  9  Processing ore from the Peak Gold Project at Fort Knox avoids mill construction and is expected to decrease execution risk, lower capital expenditures, drive attractive returns, and reduce the project’s environmental footprint and permitting requirements.  Leverages Fort Knox’s successful 25-year history in Alaska, the second largest gold producing State in the USA and one of the world’s top mining jurisdictions1.  Project to benefit local communities, particularly the Upper Tanana Athabascan Village of Tetlin; Tetlin Tribe to receive royalties, jobs and training.  Project is expected to contribute to the state economy and provide additional employment opportunities and benefits.  PROJECT HIGHLIGHTS  1 Based on Fraser Institute Annual Survey of Mining Companies, 2019 report.  Images used with permission from Kinross 
 

 10  Manh Choh Update  Construction underway 
 

 11  Manh Choh Update  Construction underway 
 

 12  Manh Choh Update - Construction underway 
 

 13  Manh Choh Update - Construction underway 
 

 14  Manh Choh Update - Construction underway 
 

 15  Manh Choh Update – Camp Construction underway 
 

 16  Manh Choh Update – Camp Construction underway 
 

 Manh Choh Update – Camp Construction underway  17 
 

 18  Manh Choh Update – Community Engagement 
 

 19   MANH CHOH GOLD PROJECT  Benefits to Alaska Residents and Businesses with smaller Environmental Footprint   McKinley Research confirms jobs, economic boost to Tok, road and infrastructure enhancements, and taxes:  • 250 to 300 new Construction jobs  • 400 to 600 direct Mine and Trucking jobs plus indirect and induced jobs (2X)  • The average annual wage estimated at $130,000 + benefits  • Once in production, Manh Choh will be the second largest private employer in SE Fairbanks area  • Manh Choh plans to purchase +$500 Million of goods and services in Alaska over 4.5 year mine life  • The Native Village of Tetlin will earn royalties  • Construction of a new cellular tower to support mine operations will benefit local communities  • Manh Choh is expected to donate several million dollars to local community benefits, such as investment in training, education, scholarships, or sponsorships 
 

 20  LOWER RISK & REDUCED TIMELINE TO PRODUCTION DECISION  DRILLING  SCOPING STUDY  PERMITTING & FEASIBILITY  PRODUCTION  DETAILED DESIGN PROCURMENT  CONSTRUCTION  $19 million Program in 2021: Resource In-fill, Hydrology, Geotechnical, Metallurgical Engineering; Environment and Community Outreach  With ~$2 million Exploration drilling to potentially expand the mine life  Tetlin Tribe has indicated their support for the project development plan;  Continued Community Engagement  $25.6 million 2022 budget approved and amended to $39.6 million   Kinross Feasibility Study completed and Permitting activities are advancing well;   Wetlands Dredge and Fill (404) Permit from USACE;   Other Permits Issued by State of Alaska  Main Project construction decision announced in July 2022  Production expected to commence in 2024  Image used with permission from Kinross  Community Engagement 
 

 PEAK GOLD LLC  21  Exploration Highlights   Completed ~$3.0 million exploration program Q4 2020 primarily directed at metallurgical and geotechnical drilling, and on-going environmental studies to advance feasibility and permitting  Completed ~$3 million in 2021 exploration program and conducted resource in-fill and condemnation drilling, hydrology, geotechnical metallurgy studies along with engineering and environmental studies to support completion of a feasibility and permitting.  528 Core and RC holes in the database with 394 drill holes used for modeling is including 69,574 m (228,260 ft) of assays.   Approved $3 million exploration program to complete regional stream sediment and pan concentrate sample, geologic reconnaissance with 1,348 samples collected (607 stream sediment, 518 soils, and 223 rocks) and approximately 8500 ft (2600 meter) drill program on Chief Danny area targets   OPEN 
 

 22  MANH CHOH GOLD PROJECT AND SURROUNDING TARGETS  Main MC  North MC  $3 Million Exploration Program Planned for 2022  Exploration for New Resources in Chief Danny Area – 4000 meters (13,000 ft) in 15 to 20 holes  Further evaluation of 685,000 acre Manh Choh property   Additional regional stream sediment sampling  Geologic mapping   Geophysical surveys including detailed ground gravity survey  
 

 ASSET SUMMARY  23  Peak Gold Project  ~(675,000 Acres)  State Claims  (~160,000 Acres)  The Manh Choh project consists of a ~685,000 acres land package including ~13,423 acres of State Mining Claims    Roughly the size of Rhode Island  Contango is also the 100% owner of the Alaska state claims exploration land package (~160,000 acres)  Peak Gold JV  70%  30%  100%  State Mining Claims Part of PGLLC  100% Contango ORE 
 

 24  1 Hart, C.J.R., 2005. Mid-Cretaceous Magmatic Evolution and Intrusion-related Metallogeny of the Tintina Gold Province, Yukon and Alaska. Unpublished PhD thesis, University of Western Australia, 198 p.  1 
 

 Lucky Shot Portal  Circa 1930  25 
 

 Lucky Shot Portal  Circa 1930  26 
 

 Lucky Shot Property Historic Resources1  Historic M&I Reserve on Adjacent Coleman Segment of LS Vein:   206k Tonnes @ 18.3 g/t Gold for 121,500 Ounces of Contained Gold2  1 The historical production information presented is based upon reports file by the US Geological Survey from information provided by prior owners and operators of the mines. The Company has not undertaken any independent work to verify or confirm the previously reported information ( see Harlan, et al., 2017 and Stoll, 1997). The historical information may not be representative of future results of the Company’s activities  2 Based on a 2016 pre-feasibility study by Hard Rock Consulting. A qualified person (as defined by Securities and Exchange Commission rules) has not done sufficient work to classify the estimate as a current estimate of mineral resources, mineral reserves or exploration results. The Company is not treating these estimates as current estimates of mineral resources, mineral reserves or exploration results. The historical information may not be representative of future results of the Company’s activities  Willow Creek district historically produced 19 metric tonnes or approximately 610,874 troy ounces from ore ranging between 30 and 60g/t making it the third largest historic lode gold producing district in Alaska (Harlan, et al., 2017)   Lucky Shot Mine reported 252,000 ozs from 169,000 tons of free-milling ore indicating an average head grade of 40 g/t (1.6 oz/tonne) (Stoll, 1997), with additional production from the Coleman and War Baby mines.   Resource Table from 2016 PFS  27 
 

 Lucky Shot Vein: +1 mile (1.6 km) strike length and open along strike and down dip  28  Coleman Adit  Lucky Shot “500” Adit  War Baby Adit  Looking NNE  Enserch Tunnel 
 

 29 
 

 30 
 

 31 
 

 Lucky Shot Update - Safety First Approach  32 
 

 Safety Reporting for Contango  Safety – Keeping Us Healthy & Safe by getting to the root of the problem  33  Lucky Shot is an Active Mine Site and so follows all Mine Safety and Health Administration (MSHA) Reporting  Preparing for Winter and Avalanche Season  The most important thing to come out of a mine is its Employees 
 

 Contango Exploration Plan for Lucky Shot Project  Rehab and extend existing Enserch tunnel to explore the Lucky Shot vein down-dip - prep for exploration drilling in three stages:  Stage 1a Drift 500 meters along footwall and parallel to vein for detailed in-fill drilling;  Stage 1b Continue Enserch tunnel as a ramp into hanging wall side of vein and drill a second panel down dip on Lucky Shot vein  Stage 2: Connect Enserch and Lucky Shot tunnels  Stage 3: Access historic M&I Resources 1 at Coleman zone by building a ramp from the Enserch level to the Coleman level in an effort to add ounces to the mine plan   Evaluate District Scale potential  Objective:  Define 500,000 ounces of gold resource by drilling Lucky Shot vein down dip from historically produced 250,000 ounces averaging 40g/t 1   34  1 The historical production information presented is based upon reports filed by the prior owners and operators of the mines. The Company has not undertaken any independent work to verify or confirm the previously reported information. 
 

 35  Lucky Shot – Enserch Tunnel Location of Pilot Holes  Exploration drill located here  Started exploration/pilot hole  Completed drill ten (10) holes in a fan pattern  Holes are 600 to 1100 feet in length  Extend tunnel to intersect the vein and bulk sample  Tunnel is currently at ~2405ft  Western Crosscut Drift Underway 
 

 36  Lucky Shot – Pilot Hole Drill Holes  10 holes completed to date from Western & Eastern Ballrooms   All 10 holes intersecting the Lucky Shot Vein  4 contained Visible Gold (VG) ASSAYS PENDING!  Complete 3 holes from Tunnel Face  Extend tunnel to intersect the vein and bulk sample 
 

 Fault  Lucky Shot vein  VG  VG  VG  VG 
 

 38  Partnered with Proven Operator  Plan to truck ore to Fort Knox mill simplifies permitting and execution  Kinross has proven operating experience in Alaska further reducing risk  The plan lowers the required capital and shortens timelines to production by leveraging existing infrastructure  High grade open pit production expected to result in strong free cash flows  Creating Shareholder Value  Strong management that has created significant value for shareholders  Planned listing on NYSE American Exchange   Clear path to production decision  Uniquely positioned for growth  Growth with Exploration Success  Significant exploration potential on the Peak Gold JV lands as well as the 100% owned State of Alaska mining claims adjacent to the future operation  DEVELOPING ALASKA’S NEXT GOLD MINES   IN PARTNERSHIP WITH KINROSS AND THE TETLIN ALASKA NATIVE TRIBE  WITH CONTINUED EXPLORATION TO EXPAND RESOURCES 
 

 39  THANK YOU 
 

 

 Lucky Shot – Underground Development to support 2022 Exploration Program and Year-Round Operations  41 
 

 Lucky Shot – Enserch Tunnel Refurbishment & Extension Plan with New Mining Equipment  42 
 

 43  Lucky Shot – Currently Advancing Towards Drift Parallel and in Footwall to Lucky Shot Vein – Exploration Drilling to Start in June 
 

 44  Lucky Shot – Underground Exploration Drill Rig 
 

 Lucky Shot – Underground Exploration Drill Rig  45 
 

 Corporate Inquires:info@contangoore.com+1-778-386-6227www.contangoore.com  NYSE American: CTGO  Twitter: @orecontangoLinkedIn: Contango OREInstagram: ContangoOREFacebook: Contango ORE 
 

 This presentation contains forward looking estimates of all-in sustaining cost (“AISC”), resources and EBITDA, which are a financial measure not determined in accordance with United States generally accepted accounting principles (“GAAP”).  We cannot provide a reconciliation of estimated AISC, resources, EBITDA and cash flow to estimated costs of goods sold, assets and net income, which are the GAAP financial measures most directly comparable to such non-GAAP measures, without unreasonable efforts due to the inherent difficulty and impracticality of quantifying certain amounts that would be required to calculate projected AISC, resources, EBITDA.  In addition, the estimates of AISC, resources and EBITDA have been prepared by Kinross and are based on IFRS accounting standards and detailed information to which the Company has not had access to at this time. These amounts that would require unreasonable effort to quantify could be significant, such that the amount of projected GAAP cost of goods sold, assets and net income would vary substantially from the amount of projected AISC, resources and EBITDA.  47  NON-GAAP RECONCILIATION DISCLAIMER  APPENDIX