Note 6 - Facility Relocation
12 Months Ended
Mar. 31, 2018
Notes to Financial Statements  
Restructuring and Related Activities Disclosure [Text Block]
Note
6.
Facility Relocation
 
In
August 2016,
we announced that we plan to shut down both our Omaha and Traverse City manufacturing facilities and relocate those operations to the new Bozeman building. The move of these
two
facilities, along with the current Bozeman operations, began in
March 2017
and is estimated to be completed by
June 30, 2018.
We estimate that the total costs of the relocation will be
$2,000,000,
which is comprised primarily of facility moving expenses, retention bonuses for existing personnel and payroll costs for duplicative personnel during the transition period. We incurred
$842,000
and
$725,000
of these relocation expenses during the years ended
March 31, 2018
and
2017,
respectively which are reflected in cost of revenues in the accompanying consolidated statements of operations (other than
$269,000
and
$45,000,
respectively which are included in general and administrative expenses). Facility relocation costs, which are associated with our Sterilization and Disinfection Control segment, are as follows for the year ended
March 31, 2018:
 
 
Retention bonuses for existing personnel of
$350,000
 
Duplicative employment costs of
$122,000
 
Moving costs of
$370,000
 
Facility relocation amounts accrued and paid for the year ended
March 31, 2018
are as follows (in thousands):
 
   
March 31,
201
8
 
Beginning balance at March 31, 2017
  $
673
 
Facility relocation expense
   
842
 
Cash payments
   
(1,107
)
Ending balance at March 31, 2018
  $
408