XML 24 R13.htm IDEA: XBRL DOCUMENT v3.10.0.1
Note 5 - Facility Relocation
9 Months Ended
Dec. 31, 2018
Notes to Financial Statements  
Restructuring and Related Activities Disclosure [Text Block]
Note
5
.
Facility Relocation
 
In
August 2016,
we announced that we planned to shut down both our Omaha and Traverse City manufacturing facilities and relocate those operations to the new Bozeman building. The move of those
two
facilities, along with the current Bozeman operations, began in
March 2017
and was completed as of
June 30, 2018.
The total cost of the relocation was
$1,584
(which is comprised primarily of facility moving expenses, retention bonuses for existing personnel and payroll costs for duplicative personnel during the transition period) and these costs pertain to the Sterilization and Disinfection Control Division.
 
Facility relocation amounts accrued and paid for the
nine
months ended
December 30, 2018
are as follows:
 
Balance at March 31, 2018
   
408
 
Facility Relocation Expense
   
17
 
Cash payments
   
(425
)
Balance at December 31, 2018
   
-
 
 
We completed the sale of our old Bozeman facility during the
nine
months ended
December 31, 2018,
for
$2,222
(net of commissions) resulting in a gain of
$288,
which is recorded in other (income) expense, net on our condensed consolidated statements of operations.