XML 27 R14.htm IDEA: XBRL DOCUMENT v3.21.2
COMMITMENTS AND CONTINGENCIES
9 Months Ended
Sep. 30, 2021
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES

8. COMMITMENTS AND CONTINGENCIES

 

Facility Leases

 

The Company primarily leases office facilities under operating lease arrangements that will end in various years through July 2024.

 

On June 7, 2019, we entered into a building lease agreement (the “New Lease”) with Jamboree Center 4 LLC (the “Landlord”). Pursuant to the New Lease, we have leased approximately 8,293 square feet of office space in Irvine, California. The New Lease commenced on August 1, 2019. The term of the New Lease is 60 months from the commencement date, provides for annual rent increases, and does not provide us the right to early terminate or extend our lease terms.

  

On January 7, 2020, we entered into a building lease agreement (the “New York Office Lease”) with Sage Realty Corporation (the “New York Office Landlord”). Pursuant to the New York Office Lease, we have leased approximately 4,000 square feet of office space for our corporate headquarters in New York, New York. The New York Office Lease commenced on February 1, 2020. The term of the New York Office Lease is 24 months from the commencement date, provides for annual rent increases, and does not provide us the right to early terminate or extend our lease terms. During August 2021, we entered into a first amendment of the New York Office Lease, to commence for a period of three years upon landlords’ substantial completion of adequate substitution space, as defined. To date, the substitution space is not ready for use, accordingly the term extension has not begun.

 

Operating lease costs were $155,000 and $174,000 for the three months ended September 30, 2021 and 2020, respectively, and $457,000 and $459,000 for the nine months ended September 30, 2021 and 2020, respectively.

 

The table below presents aggregate future minimum payments due under the New Lease and the New York Office Lease discussed above, reconciled to long-term lease liabilities and short-term lease liabilities (included in accrued expenses and other current liabilities) included in the consolidated balance sheet as of September 30, 2021:

     
   Operating Leases 
   (In thousands) 
Remainder of 2021  $149 
2022   370 
2023   364 
2024   218 
Thereafter    
Total minimum payments   1,101 
Less: short-term lease liabilities   (430)
Long-term lease liabilities  $671 

 

Inventor Royalties and Contingent Legal Expenses

 

In connection with the investment in certain patents and patent rights, certain of Acacia’s operating subsidiaries executed related agreements which grant to the former owners of the respective patents or patent rights, the right to receive inventor royalties based on future net revenues (as defined in the respective agreements) generated as a result of licensing and otherwise enforcing the respective patents or patent portfolios.

 

Acacia’s operating subsidiaries may retain the services of law firms that specialize in patent licensing and enforcement and patent law in connection with their licensing and enforcement activities. These law firms may be retained on a contingent fee basis whereby such law firms are paid on a scaled percentage of any negotiated fees, settlements or judgments awarded based on how and when the fees, settlements or judgments are obtained.

 

Patent Enforcement

 

Certain of Acacia’s operating subsidiaries are often required to engage in litigation to enforce their patents and patent rights. In connection with any of Acacia’s operating subsidiaries’ patent enforcement actions, it is possible that a defendant may request and/or a court may rule that an operating subsidiary has violated statutory authority, regulatory authority, federal rules, local court rules, or governing standards relating to the substantive or procedural aspects of such enforcement actions. In such event, a court may issue monetary sanctions against Acacia or its operating subsidiaries or award attorney’s fees and/or expenses to a defendant(s), which could be material.

 

Acacia is subject to claims, counterclaims and legal actions that arise in the ordinary course of business. Management believes that the ultimate liability with respect to these claims and legal actions, if any, will not have a material effect on Acacia’s consolidated financial position, results of operations or cash flows.

 

In December 2017, the Federal Court of Canada allowed a counterclaim for invalidity of a patent asserted by Rapid Completions LLC and awarded costs payable by Rapid Completions LLC in amounts that are included in the 2021 and 2020 accrual balances discussed below. During the three months ended September 30, 2021, the Company made approximately $1.0 million in settlement payments.

 

On September 6, 2019, Slingshot Technologies, LLC, or Slingshot, filed a lawsuit in Delaware Chancery Court against the Company and Acacia Research Group, LLC, or collectively, the Acacia Entities, Monarch Networking Solutions LLC (“Monarch”), Acacia board member Katharine Wolanyk, and Transpacific IP Group, Ltd., or Transpacific. Slingshot alleges that the Acacia Entities and Monarch misappropriated its confidential and proprietary information, purportedly furnished to the Acacia Entities and Monarch by Ms. Wolanyk, in acquiring a patent portfolio from Transpacific after Slingshot’s exclusive option to purchase the same patent portfolio from Transpacific had already expired. Slingshot seeks monetary damages, as well as equitable and injunctive relief related to its alleged right to own the portfolio. On March 15, 2021, the court issued orders granting Monarch’s motion to dismiss for lack of personal jurisdiction and Ms. Wolanyk’s motion to dismiss for lack of subject matter jurisdiction. The remaining parties then commenced discovery, and have since served initial written requests and responses, and notices of the depositions of the parties’ corporate designees. The Acacia Entities maintain that Slingshot’s allegations are baseless, that the Acacia Entities neither had access to nor used Slingshot’s information in acquiring the portfolio, that the Acacia Entities acquired the portfolio as a result of the independent efforts of its IP licensing group, and that Slingshot suffered no damages given its exclusive option to purchase the portfolio had already ended and it has proven itself incapable of closing on the portfolio purchase.

 

During the three months ended September 30, 2021 and 2020, there were no operating expenses related to settlement and contingency accruals. During the nine months ended September 30, 2021, we incurred $338,000 in operating expenses for settlement and contingency accruals. During the nine months ended September 30, 2020, operating expenses included a net income for settlement offset by contingency accruals totaling $308,000, net of prior accruals. At September 30, 2021 and December 31, 2020, our contingency accrual balance was $587,000 and $1.3 million, respectively.