Facility and Equipment Leases

The Company leases its headquarters in San Jose, California, and also leases office space under non-cancelable operating leases in various domestic and international locations. During the first quarter of fiscal 2019 as it commenced the build-out of its new corporate headquarters, the Company began to record additional straight-line rent expenses. Total rent expense for the three months ended June 30, 2018 and 2017 was $2.6 million and $1.4 million, respectively. Future minimum annual lease payments as of June 30, 2018 were as follows (in thousands):

      Amount
Remaining 2019   $ 4,314 
2020     6,622 
2021     8,961 
2022     8,848 
2023     8,353 
     Thereafter     54,724 
     Total   $ 91,822 

 

The Company has entered into a series of noncancelable capital lease agreements for data center and office equipment bearing interest at various rates.

Other Commitments, Indemnifications and Contingencies

There were no material changes in our other commitments under contractual obligations, indemnification and other contingencies since March 31, 2018.

Legal Proceedings

The Company, from time to time, is involved in various legal claims or litigation, including patent infringement claims that can arise in the normal course of the Company's operations. Pending or future litigation could be costly, could cause the diversion of management's attention and could upon resolution, have a material adverse effect on the Company's business, results of operations, financial condition and cash flows.