Note 5 - Advances for Vessels Under Construction and Acquisitions
12 Months Ended
Dec. 31, 2012
Advances For Vessels Under Construction And Acquisitions [Text Block]
5.
Advances for Vessels Under Construction and Acquisitions

The amounts shown in the accompanying consolidated balance sheets as of December 31, 2011 and December 31, 2012 of $22,347,811 and $19,321,045, mainly represent advance payments to a ship-builder for two LPG carriers under construction and to sellers for four LPG carriers under construction, respectively (see Note 3).

The movement of the account, advances for vessels under construction and acquisitions, for the years ended December 31, 2011 and 2012, was as follows:

Balance, December 31, 2010
    37,273,199  
Advances for vessels under construction and acquisitions
    52,797,646  
Capitalized interest
    557,565  
Capitalized expenses
    1,625,979  
Vessels delivered
    (69,906,578 )
Balance, December 31, 2011
    22,347,811  
Advances for vessels under construction and acquisitions
    61,632,129  
Capitalized interest
    281,484  
Capitalized expenses
    721,220  
Vessels delivered
    (65,661,599 )
Balance, December 31, 2012
    19,321,045  

On February 25, 2008, the Company signed contracts with Mitsubishi Corporation of Japan for the construction of five LPG carriers at an aggregate contract price of Yen 12,008,000,000 (approx. $124,486,017 based upon an aggregate average USD/JPY exchange rate of $1.00:JPY 96.46). Pursuant to an agreement signed on February 27, 2009, the vessels were scheduled for delivery between February 2011 and May 2012. On June 18, 2010, the Company signed a further agreement with the shipyard which provides for a 5% reduction of the contract price of each vessel under construction. This reduction was deducted from the final installment due upon delivery of each vessel. During the years 2011 and 2012, the Company effected advance payments to the shipbuilding yard of $52,797,646 and $42,432,106, respectively. Three of the five LPG carriers were delivered to the Company in 2011 and the remaining two LPG carriers in 2012 (Note 6).