Note 4 - Rates and Regulatory Matters
6 Months Ended
Mar. 31, 2024
Notes to Financial Statements  
Public Utilities Disclosure [Text Block]

4.

Rates and Regulatory Matters

 

The SCC exercises regulatory authority over the natural gas operations of Roanoke Gas. Such regulation encompasses terms, conditions and rates to be charged to customers for natural gas service, safety standards, service extension and depreciation.

 

In response to continued inflationary pressures, Roanoke Gas filed a general rate application on February 2, 2024 with the SCC seeking to increase its non-gas base rates by $4.33 million and sought to increase its permitted rate of return from 9.44% to 10.35% reflecting its higher cost of capital, including continued increases in interest rates.  The new rates will go into effect for customer billings on or after July 1, 2024, subject to refund.  The SCC’s review of Roanoke Gas’ filing is underway and a hearing has been set for November 7, 2024.

 

On December 2, 2022, Roanoke Gas filed an expedited rate application with the SCC seeking an $8.55 million annual increase in its non-gas base rates, of which $4.05 million was being recovered through the SAVE Rider.  The proposed rates went into effect January 1, 2023, subject to refund.  In the fourth quarter of fiscal 2023, the Company reached a settlement with the SCC staff on all outstanding issues in the case.  Under the terms of the settlement, the Company agreed to an incremental revenue requirement of $7.45 million. The Company agreed to begin billing the new rates effective October 1, 2023. The Commission issued its Final Order in the matter on December 19, 2023 in which it approved the settlement agreement in its entirety.  Refunds, which had previously been accrued, were made to customers in February 2024.

 

On August 31, 2023, the SCC approved the new SAVE Plan and Rider with rates effective October 1, 2023.  Under this plan, Roanoke Gas can recover costs associated with an estimated $8.5 million in SAVE eligible investment in fiscal 2024 and an estimated cumulative investment of $49.5 million over the proposed five-year plan period ending September 30, 2028.  The plan was approved with a revenue requirement of approximately $366,000 for fiscal 2024.

 

Roanoke Gas is authorized by the SCC to acquire certain natural gas distribution assets from a local housing authority at five separate apartment complexes, located in the Company’s service territory.  The housing authority renews existing natural gas distribution facilities to include mains and services then transfers ownership of these facilities to Roanoke Gas.  In turn, Roanoke Gas assumes responsibility for the operation and maintenance of these assets and recognizes a gain related to the asset acquisition equal to the cost associated with the renewal.

 

The assets of two complexes were transferred to Roanoke Gas in fiscal 2022.  On September 29, 2023, the housing authority transferred the assets from one additional apartment complex to Roanoke Gas and the Company recorded a pre-tax gain of approximately $311,000 during the fourth quarter of fiscal 2023.  The authority is underway with renewing the fourth complex and is awaiting future funding to complete the remaining apartment complex.  The timing of funding and the completion of the asset renewals for these complexes is uncertain at this time.