XML 19 R9.htm IDEA: XBRL DOCUMENT v3.3.0.814
Mineral Properties
9 Months Ended
Sep. 30, 2015
Mineral Properties [Abstract]  
Mineral Properties

3. Mineral Properties

 

 

 

 

 

 

 

 

 

 

    

At September 30, 2015

    

At December 31, 2014

 

Mt Todd, Australia

 

$

2,146

 

$

2,146

 

Guadalupe de los Reyes, Mexico

 

 

1,728

 

 

2,224

 

Los Cardones, Mexico

 

 

 —

 

 

1,036

 

 

 

$

3,874

 

$

5,406

 

 

Guadalupe de los Reyes Gold/Silver Project, Sinaloa, Mexico

 

During April 2014, Minera Gold Stake S.A. de C.V. (“MGS”), Vista’s wholly-owned subsidiary, entered into a definitive option agreement (the “Option Agreement”) to option a 70% interest in the Guadalupe de los Reyes gold/silver project in Sinaloa, Mexico to Great Panther Silver Limited (formerly Cangold Limited) (“Great Panther”) for consideration of $5,000 in payments over a three-year period, with payments totaling $1,000 in the first year ($500 received in 2014 and $496 net of legal costs was received in March 2015), $1,500 in January 2016 and $2,500 in January 2017.

 

The Option Agreement provides that all cash payments are non-refundable and optional to Great Panther, and in the event Great Panther fails to pay any of the required amounts on the scheduled dates or fails to comply with its other obligations, the Option Agreement will terminate and Great Panther will have no interest in the Guadalupe de los Reyes gold/silver project. Provided it is not in breach of the Option Agreement, Great Panther may at its discretion advance the above payment schedule and exercise the initial option for a 70% interest in the Guadalupe de los Reyes gold/silver project any time during the three-year period.

 

Subject to Great Panther earning a 70% interest in the Guadalupe de los Reyes gold/silver project, MGS has granted Great Panther the option to earn the remaining 30% interest in the Guadalupe de los Reyes gold/silver project by notifying MGS of a production decision no later than the tenth anniversary of exercising the first option and by making a cash payment to MGS of $3,000 plus an additional cash payment based on a formula that includes the growth, if any, in estimated measured and indicated mineral resources of the Guadalupe de los Reyes gold/silver project, and the then prevailing spot gold price (“Escalator Payment”).

 

Should Great Panther determine not to put the Guadalupe de los Reyes gold/silver project into production, the Option Agreement provides MGS with the right to buy back Great Panther’s 70% interest in the Guadalupe de los Reyes gold/silver project for a cash payment of $5,000 plus the Escalator Payment described above.  If MGS does not exercise its buyback option, MGS will still retain a right of first refusal should Great Panther elect to sell its 70% interest in the Guadalupe de los Reyes gold/silver project to a third party.

 

Los Cardones

 

In October 2013, we sold our 100% debt and equity participation in the Los Cardones gold project located in Baja California Sur, Mexico (“Los Cardones Sale”) to Invecture Group, S.A. de C.V. (“Invecture”) and RPG Structured Finance S.a.r.l. (together the “Purchasers”) for a total of $13,000 ($7,000 of which was paid in October 2013 and $6,000 of which was originally payable in January 2014 (the “Subsequent Payment”) subject to the Purchasers’ option to elect to not make the Subsequent Payment).  In 2014, the due date for the Subsequent Payment was extended to January 30, 2015 for additional consideration of $500.  In October 2014, Invecture announced that the Los Cardones gold project had been suspended because the conditions for its development were not favorable at that time, which introduced substantial doubt that the Subsequent Payment would be made.  After making this announcement, there were no apparent significant favorable changes to incentivize Invecture to lift the suspension. In January 2015, we agreed to amend the payment terms (the “Amendment”) of the Los Cardones Sale. Under the Amendment, the Company received a payment of $496 net of legal costs from the Purchasers as the final payment for 100% of the Company’s interest in the project.  This resulted in a realized gain of $1,958.