We are subject to various claims and contingencies in the normal course of business. In addition, from time to time, we receive communications from government or regulatory agencies concerning investigations or allegations of noncompliance with laws or regulations in jurisdictions in which we operate. At a minimum we disclose such matters if we believe it is reasonably possible that a future event or events will confirm a loss through impairment of an asset or the incurrence of a liability. We accrue a loss if we believe it is probable that a future event or events will confirm a loss and we can reasonably estimate such loss and we do not accrue future legal costs related to that loss. Furthermore, we will disclose any matter that is unasserted if we consider it probable that a claim will be asserted and there is a reasonable possibility that the outcome will be unfavorable. We expense legal defense costs as they are incurred.

On December 13, 2013, we and our wholly-owned subsidiaries, Tertiaire Resources Company and NGS Sub. Corp., filed a lawsuit in the 133rd Judicial District Court of Harris County, Texas, against Denbury Onshore, LLC (“Denbury”) alleging breaches of certain 2006 agreements between the parties regarding the Delhi field in Richland Parish, Louisiana. The specific allegations include improperly charging the payout account for capital expenditures and costs of capital, failure to adhere to preferential rights to participate in acquisitions within the defined area of mutual interest, breach of the promises to assume environmental liabilities and fully indemnify us from such costs, and other breaches. We also alleged that Denbury’s gross negligence caused certain environmental damage to the unit.  Specifically, we allege that Denbury failed to properly conduct CO2 injection activities. We are seeking declaration of the validity of the 2006 agreements and recovery of damages and attorneys’ fees. Denbury subsequently filed counterclaims, including the assertion that we owe Denbury additional revenue interests pursuant to the 2006 agreements and that our transfers of the reversionary interests from our wholly owned subsidiary to our parent corporation and subsequently to another wholly-owned subsidiary were not timely noticed to Denbury. The Company disagrees with, and is vigorously defending against, Denbury's counterclaims. In March 2015, we amended and expanded our claims in this matter. This matter is currently scheduled for trial in late July 2016.

On December 3, 2013, our wholly owned subsidiary, NGS Sub Corp., was served with a lawsuit filed in the 8th Judicial District Court of Winn Parish, Louisiana by Cecil M. Brooks and Brandon Hawkins, residents of Louisiana, alleging that in 2006 a former subsidiary of NGS Sub Corp. improperly disposed of water from an off-lease well into a well located on the plaintiffs’ lands in Winn Parish. The plaintiffs requested monetary damages and other relief. NGS Sub Corp. divested its ownership of the property in question along with its ownership of the subsidiary in 2008 to a third party. The district court granted our exception of no right of action and dismissed certain claims against NGS Sub Corp. The plaintiffs subsequently filed an amended petition naming NGS Sub Corp. and the Company as defendants. NGS Sub Corp. and the Company have denied the plaintiffs’ claims. Various pretrial motions filed on behalf of multiple parties were recently decided by the court and discovery is in process. We will continue to vigorously defend all claims by plaintiffs and consider the likelihood of a material loss to the Company in this matter to be remote.
 
Lease Commitments.  We have a non-cancelable operating lease for office space that expires on July 31, 2016. Future minimum lease commitments as of March 31, 2016 under this operating lease are as follows: 
Twelve months ended March 31,
 
2016
$
53,004


 
Rent expense for the three months ended March 31, 2016 and 2015 was $46,286 and $43,776, respectively. For the nine months ended March 31, 2016 and 2015, rent expense was $137,185 and $131,327. Subsequent to the end of the quarter, we signed a letter of intent for smaller, less expensive office space to replace our current lease.

Capital Expenditures. See Note 5 for discussion of capital projects in progress and expected remaining capital commitments.