16. CONTINGENCIES

 

Litigation and Claims

 

The Company is from time to time party to various lawsuits, claims and other proceedings that arise in the ordinary course of our business.

 

On January 11, 2016, Myers Power Products, Inc., a specialty electrical products manufacturer, filed suit with the Superior Court of the State of California, County of Los Angeles, against us, PCEP and two PCEP employees who are former employees of Myers Power Products, Inc., Geo Murickan, the president of PCEP (“Murickan”), and Brett DeChellis (“DeChellis”), alleging, among other things, that Murickan wrongly used and retained confidential business information of Myers Power Products, Inc. for the benefit of us and PCEP, in breach of their confidentiality agreement and/or employment agreement entered into with Myers Power Products, Inc., and that we and PCEP knowingly received and used such confidential business information. Myers Power Products, Inc. is seeking injunctive relief enjoining us, PCEP and our employees from using its confidential business information and compensatory damages of an unspecified unlimited amount (exceeding $25,000); however, the Company has recognized approximately $1.2 million for expected costs related to this litigation. On March 18, 2016, we filed an answer to the complaint, denying generally each and every allegation and relief sought by Myers Power Products, Inc. and seeking dismissal based on, among other things, failure to state facts sufficient to constitute a cause of action. We intend to contest the matter vigorously. Due to the uncertainties of litigation, however, we can give no assurance that we, PCEP and our employees will prevail on any claims made against us, PCEP and our employees in any such lawsuit. As of the filing of this report, this action is scheduled for trial in the first quarter of 2020. Also, we can give no assurance that any other lawsuits or claims brought in the future will not have an adverse effect on our financial condition, liquidity or operating results. We cannot execute the sale of PCEP until the lawsuit has been resolved.

 

On October 4, 2019, the dividend that was payable by the Company was enjoined by court order of the Superior Court of California related to the foregoing case. The Company continues to contest the order. As of the date of this filing, this court order remains in place. On October 16, 2019, Myers Power Products, Inc. filed an ex parte application arguing the Company had violated, or intended to violate the modified preliminary injunction and sought order from the court for the Company to post a bond in an amount of $20,000 or more. The court has not taken any action on this request and the Company intends to vigorously defend its rights in the event the order is granted.

 

With respect to all such lawsuits, claims and proceedings, the Company records a reserve when it is probable that a liability has been incurred and the amount of loss can be reasonably estimated. The Company does not believe that the resolution of any currently pending lawsuits, claims and proceedings, either individually or in the aggregate, will have a material adverse effect on its financial position, results of operations or liquidity. However, the outcomes of any currently pending lawsuits, claims and proceedings cannot be predicted, and therefore, there can be no assurance that this will be the case.