COSTS AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS
6 Months Ended
Jun. 30, 2017
Contractors [Abstract]  
COSTS AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS

4. COSTS AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS

 

Costs and estimated earnings in excess of billings on uncompleted contracts consist of:

 

   June 30, 2017 
   U.S         
   Government   Commercial   Total 
             
Costs incurred on uncompleted contracts  $357,970,228   $165,341,508   $523,311,736 
Estimated earnings   40,585,938    61,086,808    101,672,746 
Sub-total   398,556,166    226,428,316    624,984,482 
Less billings to date   349,494,171    174,720,733    524,214,904 
                
Costs and estimated earnings in excess of billings on uncompleted contracts  $49,061,995   $51,707,583   $100,769,578 

 

   December 31, 2016 
   U.S.         
   Government   Commercial   Total 
Costs incurred on uncompleted contracts  $341,003,461   $153,898,425   $494,901,886 
Estimated earnings   39,638,231    58,346,518    97,984,749 
Sub-total   380,641,692    212,244,943    592,886,635 
Less billings to date   331,277,942    162,145,504    493,423,446 
                
Costs and estimated earnings in excess of billings on uncompleted contracts  $49,363,750   $50,099,439   $99,463,189 

 

The above amounts are included in the accompanying condensed balance sheets under the following captions at June 30, 2017 and December 31, 2016:

 

   June 30, 2017   December 31, 2016 
Costs and estimated earnings in excess of billings on uncompleted contracts  $101,692,410   $99,578,526 
Billings in excess of costs and estimated earnings on uncompleted contracts   (922,832)   (115,337)
           
Totals  $100,769,578   $99,463,189 

 

U.S. Government Contracts include contracts directly with the U.S. Government and Government subcontracts.

 

Revisions in the estimated gross profits on contracts and contract amounts are made in the period in which the circumstances requiring the revisions occur. During the six months ended June 30, 2017, the effect of such revisions in total estimated contract profits resulted in a decrease to the total gross profit to be earned on the contracts of approximately $1,627,000 from that which would have been reported had the revised estimates been used as the basis of recognition of contract profits in prior years, excluding the effect of the A-10 contract. During the six months ended June 30, 2016, the effect of such revisions was a decrease to total gross profit of approximately $1,171,000.

 

Although management believes it has established adequate procedures for estimating costs to uncompleted open contracts, it is possible that additional significant costs could occur on contracts prior to completion.