XML 35 R24.htm IDEA: XBRL DOCUMENT v3.10.0.1
18. SUBSEQUENT EVENTS
9 Months Ended
Sep. 30, 2018
Subsequent Events [Abstract]  
SUBSEQUENT EVENTS

On October 4, 2018, the Company signed a bromine well reconstruction contract with a total contract amount of approximately $5.9 million to replace damaged wells caused by flooding from a typhoon that hit the Shandong Province of PRC in August 2018. The Company also signed a maintenance contract on October 4, 2018 with a total contract amount of approximately $2.6 million to repair damaged aqueduct, halogen reservoirs, and roads caused by the floods.

 

On October 17, 2018, the Company signed a one-time land compensation agreement of approximately $0.2 million for the construction of wastewater discharge channels of bromine factory Number 10.

 

On October 22, 2018, the Company signed the wastewater drainage and treatment project contract with a total contract amount of approximately $5.1 million. It mainly provides additional wastewater treatment for the Company's factory Number 1, Number 2 and Subdivision of Factory Number 1. 


On October 31, 2018, the Company signed the wastewater drainage and treatment project contract with a total contract amount of approximately $0.81 million. It mainly provides wastewater treatment for the Company's factory Number 10.