1. ORGANIZATION AND DESCRIPTION OF BUSINESS

 

China Recycling Energy Corporation (the “Company” or “CREG”) was incorporated on May 8, 1980, under the laws of the State of Colorado. On September 6, 2001, the Company re-domiciled its state of incorporation to Nevada. The Company, through its subsidiaries, Shanghai TCH Energy Technology Co., Ltd (“Shanghai TCH”) and Huahong New Energy Technology Co, Ltd (Huahong), provides energy saving solution and services, including selling and leasing energy saving systems and equipment to customers.  On March 8, 2007, the Company changed its name to “China Recycling Energy Corporation” from “China Digital Wireless, Inc.”

 

On February 1, 2007, the Company’s subsidiary, Shanghai TCH, conditionally entered into two top gas recovery turbine systems (the “TRT”) projects, each evidenced by a joint-operation agreement, with Xi’an Yingfeng Science and Technology Co., Ltd. (the “Yingfeng”). TRT is an electricity generating system that utilizes exhaust pressure and heat produced in the blast furnace of a steel mill to generate electricity.

 

Under these two Joint-Operation Agreements, Shanghai TCH and Yingfeng jointly pursued a top gas recovery turbine project (the "TRT Project") that was to design, construct, install and operate a TRT Project for Zhangzhi Iron and Steel Holdings Ltd. (the"Zhangzhi") and Xingtai Iron and Steel Company, Ltd. (the “Xingtai”), respectively. These two projects were completed and put into operation in February and August 2007, respectively

 

On October 31, 2007, Shanghai TCH entered an asset-transfer agreement with Yingfeng. The terms and conditions of this agreement required the transfer of all electricity-generating related assets owned by Yingfeng to Shanghai TCH. As a result, the contractual relationships between Shanghai TCH and Yingfeng under the TRT Project Joint-Operation Agreement on April 8, 2007 were terminated.

 

In November 2007, Shanghai TCH signed a cooperative agreement with Shengwei Group to build two sets of 12MW pure low temperature cement waste heat powered generator systems (“CHPG”) for Shengwei’s two 2,500-tons-per-day cement manufacturing lines in Jin Yang and for a 5,000-tons-per-day cement manufacturing line in Tong Chuan.  At the end of 2008, construction of the CHPG in Tong Chuan was completed and put into operation.  On June 29, 2009, construction of the CHPG in Jin Yang was completed and put into operation.

 

On April 14, 2009, the Company incorporated a joint venture (the “JV”) with Erdos Metallurgy Co., Ltd. (the “Erdos”) to recycle waste heat from Erdos’ metal refining plants to generate power and steam, which will then be sold back to Erdos. The name of the JV is Inner Mongolia Erdos TCH Energy Saving Development Co., Ltd (the “Erdos TCH”) with a term of 20 years. Total investment for the project is estimated at $79 million (RMB 500 million) with an initial investment of $17.55 million (RMB 120,000,000). As of June 30, 2012, Erdos contributed 7% of the total investment of the project, and Xi’an TCH contributed 93%. According to Xi’an TCH and Erdos’ agreement on profit distribution, Xi’an TCH and Erdos will receive 80% and 20% of the profit from the JV, respectively, until Xi’an TCH receives the complete return of its investment. Xi’an TCH and Erdos will then receive 60% and 40% of the profit from the JV, respectively. When the term of the JV expires, Xi’an TCH will transfer its equity in the JV to Erdos at no additional cost.

 

On April 18, 2009, Erdos TCH signed a Cooperation Agreement with Erdos to recycle heat from groups of furnaces of Erdos Metallurgy’s metal refining plants to generate power and steam, which will then be sold back to Erdos Metallurgy. According to the contract, Erdos TCH will install a group of power generation projects with a total of 70MW power capacity, which may expand up to 120MW, and 30-ton steam per hour, with an estimated total investment of over $79 million (RMB 500 million).  The construction of the projects was split into three phases, two power generation systems in Phase I with a total of 18MW power capacity, three power generation systems in Phase II with a total of 27MW power capacity and one power generation system in Phase III with 25MW power capacity.

 

At the end of 2009, Erdos TCH completed the first 9MW power station of Phase I of the project and put it into operation.  Phase I includes two 9MW units for a combined 18MW power capacity. In March of 2010, the Company completed the second 9MW capacity power station and put it into operation. Pursuant to the Co-operation Agreement and the supplement agreements signed between Erdos and Erdos TCH, Erdos shall purchase all the electricity and steam to be generated from the JV’s power generation projects.

 

 

On December 10, 2010, Erdos TCH entered into a supplementary agreement with Xi’an Huaxin Energy Tech Co., Ltd (the construction contractor) to change the Erdos Phase II project of four 9MW waste heat generation systems to three 9MW systems, and to move the fourth 9MW waste heat generation system into Phase III of the project; as a result of entering into this supplementary agreement, the construction costs decreased from $37.4 million (RMB248 million) to $28.1 million (RMB186 million) for the Phase II.  In the first quarter of 2011, the Company completed all three 9MW power stations of Phase II and put them into operation.

 

On September 30, 2009, Xi’an TCH delivered three 6MW capacity Waste Gas Power Generation (“WGPG”) power generating systems to Shenmu County Jiujiang Trading Co., Ltd. (“Shenmu”) pursuant to a Cooperative Contract on Coke-oven Gas Power Generation Project (including its Supplementary Agreement) the “Cooperative Agreement”) and a Gas Supply Contract for Coke-oven Gas Power Generation Project.  The terms of these contracts are for 10 years, and state that Xi’an TCH will recycle coke furnace gas from the coke-oven plant of Shenmu to generate power, which will be supplied back to Shenmu.

 

On December 31, 2011, Xi’an TCH entered into a Repurchase Agreement for the Coke-Oven Gas Power Generation Project (the “Repurchase Agreement”) with Shenmu. Under the Repurchase Agreement, Shenmu will purchase the set of 18MW capacity power generating systems (the “Systems”) from Xi’an TCH and pay outstanding energy saving service fees of $3.08 million (RMB 19.44 million) to Xi’an TCH within three working days from the date of the Repurchase Agreement. Xi’an TCH will transfer the Systems to Shenmu for $18.75 million (RMB 120 million) (the “Repurchase Price”) to be paid in three installments within 180 days. In June 2012, the Company received the full payment of outstanding energy saving service fees and system repurchase price, and, as a result, ownership of the Systems was transferred to Shenmu and the Cooperative Contract was terminated.

 

On January 20, 2010, Xi’an TCH entered into a Technical Reconstruction Letter of Intent with Xueyi Dong (“Dong”) a natural person with Chinese citizenship for Xi’an TCH reconstructing and transforming a Thermal Power Generation Systems owned by Dong into a 12MW Biomass Power Generation System (the “Biomass Systems” or “BMPG”) for $2.2 million (RMB 15 million), which was paid by Xi’an TCH to Dong. After the transformation of the system, Xi’an TCH entered into a Biomass Power Generation Asset Transfer Agreement with Dong on June 29, 2010.  Under the Transfer Agreement, Dong transferred the Biomass Systems to Xi’an TCH, and Xi’an TCH was to pay Dong $14,705,900 (RMB 100,000,000) for the systems, including RMB 20,000,000 in cash and RMB 80,000,000 in shares of the Company’s common stock. The exchange rate between U.S. Dollar and Chinese RMB in connection with the stock issuance was 1:6.8.  As of December 31, 2011, the Company had paid the cash portion and issued 2,941,176 shares of common stock. For payment in full of the RMB 80,000,000 in shares, in connection with this transaction, the Company, as of December 31, 2011, recorded a gain on settlement of the debt of $8.3 million.

 

On June 29, 2010, Xi’an TCH entered into a Biomass Power Generation Project Lease Agreement with PuCheng XinHengYuan Biomass Power Generation Co., Ltd. (“XHY”).  Under this lease agreement, Xi’an TCH leased this same set of 12MW biomass power generation systems to XHY at a minimum of $279,400 (RMB 1,900,000) per month for 15 years.

 

On September 30, 2010, Xi’an TCH delivered to Zhongbao Binhai Nickel Co., Ltd. (“Zhongbao”) a 7MW capacity Waste Heat Power Generation (“WHPG”) system, an integral part of the facilities designed to produce 80,000 tons of nickel-alloy per year according to the recovery and power generation of waste heat agreement with Zhongbao, a nickel-alloy manufacturing joint venture between Zhonggang and Shanghai Baoshan Steel Group established in June 2009.  Total investment in this project was $7.8 million (RMB 55 million). The waste heat agreement with Zhongbao has a term of nine years and provides that Xi’an TCH will recycle waste heat from the nickel-alloy rotary kilns of Zhongbao to generate power and steam, which will be supplied back to Zhongbao. In addition, Xi’an TCH is responsible for applying for the Clean Development Mechanism (“CDM”) under the Kyoto Protocol.  Net proceeds from any CDM credit will be distributed between Zhongbao and Xi’an TCH at 60% and 40%, respectively.  As of June 30, 2012, Xi’an TCH had not yet commenced the CDM application process.

 

On March 15, 2011, the Company incorporated a new wholly owned subsidiary Pingshan County Shengda Energy Technology Co., Ltd (“Shengda”). Xi’an TCH contributed cash of $4,559,271 (RMB 30 million) into Shengda as initial capital. In accordance with and pursuant to a Recycling Economy Projects Cooperative Framework Agreement entered into by the Company and Xi’an TCH, Shengda was organized for the purpose of undertaking waste energy recycling projects from a steel and chemical company located in Pingshan county. However, final terms for the projects were not reached, and, as a result, Shengda is not currently operational. In July 2012, Shengda applied for cancellation of its registration with the appropriate authorities. A liquidation of Shengda’s assets will be completed within 45 days of its announcement, July 5, 2012.

 

 

On May 25, 2011, Xi’an TCH entered into a Letter of Intent with ShenQiu YuNeng Thermal Power Co., Ltd. (“ShenQiu”) for Xi’an TCH to reconstruct and transform a Thermal Power Generation System owned by ShenQiu into a 75T/H Biomass Power Generation System for $3.5 million (RMB 22.5 million). The project commenced in June 2011, and was completed in the third quarter of 2011. On September 28, 2011, Xi’an TCH entered into a Biomass Power Generation Asset Transfer Agreement with ShenQiu. Per the Transfer Agreement, ShenQiu sold to Xi’an TCH a set of 12 MW biomass power generation systems, effectuation of such sale occurring after Xi’an TCH converted the system for biomass power generation purposes.  As consideration for the biomass power generation system, Xi’an TCH agreed to pay ShenQiu $10,937,500 (RMB 70 million) in cash in three installments within six months upon the transfer of ownership of the system. As of June 30, 2012, $9,012,000 (RMB 57,000,000) was paid by Xi’an TCH to ShenQiu, of which $7.5 million was paid in cash and $1.5 million in notes maturing on various dates from September to December 2012. In July 2012, the remaining balance of $2.1 million was paid in full. On September 28, 2011, Xi’an TCH and ShenQiu also entered into a Biomass Power Generation Project Lease Agreement (the “Lease Agreement”).  Under the Lease Agreement, Xi’an TCH agreed to lease the set of 12 MW biomass power generation systems to ShenQiu for $286,000 (RMB 1,800,000) per month for a term of 11 years. Upon completion of the Lease Agreement, ownership of this system will be transferred from Xi’an TCH to Shenqiu at no cost.

 

On June 13, 2012, Huahong, a subsidiary of the Company, obtained preliminary approval from Department of Commerce of Shaanxi Province to reduce its investment amount from $10 million to $5 million and its registered capital from $10 million to $2.5 million.

 

The unaudited financial statements included herein were prepared by the Company, pursuant to the rules and regulations of the Securities and Exchange Commission (“SEC”).  The information furnished herein reflects all adjustments (consisting of normal recurring accruals and adjustments) that are, in the opinion of management, necessary to fairly present the operating results for the respective periods. Certain information and footnote disclosures normally present in annual financial statements prepared in accordance with accounting principles generally accepted in the United States of America (“US GAAP”) were omitted pursuant to such rules and regulations. These financial statements should be read in conjunction with the audited financial statements and footnotes included in the Company’s 2011 audited financial statements included in the Company’s Annual Report on Form 10-K.  The results for the six and three months ended June 30, 2012 are not necessarily indicative of the results expected for the full year ending December 31, 2012.