XML 28 R26.htm IDEA: XBRL DOCUMENT v2.4.0.8
COMMITMENTS
12 Months Ended
Dec. 31, 2011
COMMITMENTS
20. COMMITMENTS
 
 
On March 5, 2010, Xi’an TCH leased its office under a two year operating lease that will expire on March 4, 2012. The monthly rental payment is $16,360. For the years ended December 31, 2011 and 2010, the rental expense was $209,000 and $164,000, respectively. As of December 31, 2011, the Company renewed the lease for one more year with the monthly payment increased by 8%.
 
ShangHai TCH entered into a one year renewable rental agreement to lease a virtual office effective, April 1, 2011. The monthly payment is $260. For the year ended December 31, 2011, the rental expense was $2,340. The lease will be automatically renewed when it is expired.
 
Future minimum rental payments required under operating leases as of December 31, 2011 are as follows by years:
 
2012
$
226,000
2013
38,000
$
264,800
 
 
Erdos Phase III of Power Generation Projects
 
In April 2009, Erdos TCH signed a contract with Erdos Metallurgy to recycle heat from groups of furnaces of Erdos Metallurgy’s metal refining plants to generate power and steam, to be sold back to Erdos Metallurgy. According to the contract, Erdos TCH will install a group of power generation projects with a total of 70MW power capacity, which may grow up to 120MW, and 30-ton steam per hour, with an estimated total investment in excess of $75 million (RMB 500 million). The Company split the construction of the projects into three phases, two units of power generation in Phase I with a total of 18MW power capacity, three units in Phase II with a total of 27MW power capacity and one unit in Phase III with 25MW power capacity. For each phase of the project, the lease term is 20 years starting from the date of completion of the phase. During the lease term, Erdos TCH will be responsible for operating the projects and charge Erdos Metallurgy for supply of electricity and steam. Erdos Metallurgy agreed to pay a minimum of $0.22 million (RMB 1.5 million) per month for each 9MW capacity power generation system.
 
During the first quarter of 2010, Erdos power generation system Phase I project was completed and put into operation. During the fourth quarter of 2010 and first quarter of 2011, three 9MW power generation systems of Phase II were completed and put into operation. Erdos TCH outsourced to an independent third party the operation and maintenance of the power generation system for $922,000 (RMB 6.27 million) per year for each system. After 20 years, the systems will be transferred to Erdos without any charge.
 
As of December 31, 2011, the projects of Erdos Phase III are under construction. As of December 31, 2011, the Company paid $19.77 million for Phase III of the Erdos TCH power generation system projects. The Company is committed to pay an additional $8.78 million for the Phase III projects, excluding quality deposits of $120,000 paid by the Company in 2011. In October 2011, the Company temporarily suspended construction of the 25 MW plant due to the technical transformation and renovation of certain equipment and machinery by the customer; the Company expects to resume the construction of Erdos Phase III in May 2012. The Company currently expects to complete Phase III by the end of fiscal year 2012.
 
Shannxi Datong Coal Group Power Generation Projects
 
In February 2011, Xi’an TCH signed a contract with Shannxi Datong Coal Group Steel Ltd Co (the “Shannxi Datong”) to recycle gas and steam from groups of blast-furnaces and converter of Shannxi Datong’s metal refining plants to generate power. According to the contract, Xi’an TCH will install two 3MW TRT, one 15MW WGPG and two 1MW steam power generation systems, with a total of 23MW power capacity for an estimated total investment of $27.45 million (RMB 180 million). The lease term is 30 years. During the lease term, Shannxi Datong will be responsible for operating the projects and pay service fee to Xi’an TCH. The service fee is based on an average of 8,000 electricity-generating hours per year and $0.05 (RMB 0.33) per kilowatt hour (“Kwh”) for the first 5 years from the completion of each power generation station. For each of the leases, at the 6th year, 11th year and 21st year thereafter, the rate will be RMB 0.3 Kwh, 0.27 Kwh and 0.25 Kwh, respectively. After 30 years, the units will be transferred to Shannxi Datong without any charge.
 
On February 28,2011, Xi’an TCH entered into an agreement with Xi’an Huaxin Energy Tech Co., Ltd (the contractor for construction) for Shannxi Datong Coal projects of two 3MW TRT and one 15 MW WGPG systems described above. The project is scheduled to complete in 12 months from construction commencement.
 
As of December 31, 2011, the Company had paid $12.70 million for Shannxi Datong Coal Group Power Generation project. The Company is committed to pay an additional $15.87 million for the Shannxi Datong Coal Group Power Generation project. This project is currently halted due to business reorganization of Shannxi Datong and a renegotiation of one of the power stations with Xi’an TCH to amend certain construction plans. The Company expects to resume the construction in April 2012 and complete this project by the end of 2012.