CONSTRUCTION IN PROGRESS

8. CONSTRUCTION IN PROGRESS

 

Construction in progress was for constructing power generation systems.  As of September 30, 2016 and December 31, 2015, the Company’s construction in progress included:

 

  2016  2015 
Xuzhou Zhongtai  -   28,100,201 
Xuzhou Huayu  29,633,538   29,752,270 
Xuzhou Tian’an  28,469,454   26,909,193 
Boxing County Chengli  30,900,260   30,760,404 
Total $89,003,252  $115,522,068 

 

As of September 30, 2016, the Company was committed to pay an additional (1) $7.49 million for Xuzhou Huayu project, (2) $8.65 million for Xuzhou Tian’an project, and (3) $5.40 million for Boxing County Chengli project.