CONSTRUCTION IN PROGRESS

8. CONSTRUCTION IN PROGRESS

 

Construction in progress was for constructing power generation systems. As of June 30, 2017 and December 31, 2016, the Company’s construction in progress included:

 

 2017  2016 
Xuzhou Huayu $24,090,597  $23,525,925 
Xuzhou Tian’an  34,849,365   32,471,977 
Boxing County Chengli  31,227,232   30,495,280 
Total $90,167,194  $86,493,182 

 

As of June 30, 2017, the Company was committed to pay an additional (1) $11.81 million for the Xuzhou Huayu project, and (2) $4.10 million for the Xuzhou Tian’an project. The Boxing County Chengli project finished construction, but is waiting for government approval before beginning operations.