CONSTRUCTION IN PROGRESS

8. CONSTRUCTION IN PROGRESS

 

Construction in progress was for constructing power generation systems. As of March 31, 2018 and December 31, 2017, the Company’s construction in progress included:

 

    2018     2017  
Xuzhou Huayu   $ 25,953,681     $ 24,976,178  
Xuzhou Tian’an     40,150,636       37,814,637  
Boxing County Chengli     33,642,238       32,375,158  
Total   $ 99,746,555     $ 95,165,973  

 

As of March 31, 2018, the Company was committed to pay an additional (1) $12.72 million for the Xuzhou Huayu project, (2) $4.41 million for the Xuzhou Tian’an project, and (3) $4.91 million for Boxing County Chengli project. The Boxing County Chengli project has finished construction, but is waiting for government approval before beginning operations.