Construction in Progress
6 Months Ended
Jun. 30, 2018
Construction in Progress [Abstract]  
CONSTRUCTION IN PROGRESS

8. CONSTRUCTION IN PROGRESS

 

Construction in progress was for constructing power generation systems. As of June 30, 2018 and December 31, 2017, the Company’s construction in progress included:

 

  2018  2017 
Xuzhou Huayu $24,665,136  $24,976,178 
Xuzhou Tian’an  38,979,814   37,814,637 
Boxing County Chengli  31,971,973   32,375,158 
Total $95,616,923  $95,165,973 

 

As of June 30, 2018, the Company was committed to pay an additional (1) $12.09 million for the Xuzhou Huayu project, (2) $4.19 million for the Xuzhou Tian’an project, and (3) $4.66 million for Boxing County Chengli project. The Boxing County Chengli project has finished construction, but is waiting for government approval before beginning operations.