From time to time, TVA is a party to lawsuits, claims, proceedings, investigations, and other legal matters ("Legal Proceedings") that have arisen in the ordinary course of conducting TVA's activities, as a result of a catastrophic event or otherwise.  
 
General. TVA had accrued approximately $367 million of potential losses with respect to Legal Proceedings as of June 30, 2012.  Of this amount, $251 million is included in Other long-term liabilities, $106 million is included in Accounts payable and accrued liabilities, and $10 million is included in Regulatory assets.  No assurance can be given that TVA will not be subject to significant additional claims and liabilities.  TVA has reviewed its claims, litigation and estimates and determined that the reasonably possible loss beyond the amounts accrued is an additional $6 million. If actual liabilities significantly exceed the estimates made, TVA's results of operations, liquidity, and financial condition could be materially adversely affected.
 
Environmental Agreements. In April 2011, TVA entered into two substantively similar agreements, one with the EPA and the other with Alabama, Kentucky, North Carolina, Tennessee, and three environmental advocacy groups: the Sierra Club, National Parks Conservation Association, and Our Children's Earth Foundation (collectively, the "Environmental Agreements”). They became effective in June 2011. Under the Environmental Agreements, TVA committed to (1) retire on a phased schedule 18 coal-fired units with a combined summer net dependable capability of 2,200 MW, (2) control, convert, or retire additional coal-fired units with a combined summer net dependable capability of 3,500 MW, (3) comply with annual, declining emission caps for SO2 and NOx, (4) invest $290 million in certain TVA environmental projects, (5) provide $60 million to Alabama, Kentucky, North Carolina, and Tennessee to fund environmental projects, and (6) pay civil penalties of $10 million. In exchange for these commitments, most existing and possible claims against TVA based on alleged New Source Review and associated violations are waived and cannot be brought against TVA. Some possible claims for sulfuric acid mist and greenhouse gas (“GHG”) emissions can still be brought against TVA, and claims for increases in particulates can also be pursued at many of TVA’s coal-fired units. Additionally, the Environmental Agreements do not address compliance with new laws and regulations or the cost associated with such compliance.
 
The liabilities related to the Environmental Agreements are included in Accounts payable and accrued liabilities and Other long-term liabilities on the June 30, 2012 Consolidated Balance Sheet. In conjunction with the approval of the Environmental Agreements, the TVA Board determined that it was appropriate to record TVA's liabilities under the Environmental Agreements as regulatory assets, and they are included as such on the June 30, 2012 Consolidated Balance Sheet and will be recovered in rates in future periods.
 
Several legal and administrative clean air proceedings have already been terminated in connection with the Environmental Agreements. Additionally, the proceedings discussed below involving the John Sevier and Shawnee Fossil Plant (“Shawnee”) Clean Air Act ("CAA") permits are expected to be narrowed in scope.
 
Legal Proceedings Related to the Kingston Ash Spill. Seventy-eight lawsuits based on the Kingston ash spill have been filed in the United States District Court for the Eastern District of Tennessee. Fifteen of these lawsuits have been dismissed, and 63 lawsuits are active and in various stages of litigation. Plaintiffs are residents, businesses, and property owners in the Kingston area and allege tort claims for damage to property (for example, nuisance, strict liability, trespass, and negligence), with some plaintiffs also alleging claims for personal injury, business loss, and inverse condemnation. Plaintiffs seek unspecified compensatory and punitive damages, court orders to clean up properties and other relief. TVA is the only active defendant in these actions.
 
A bench trial on the issue of dike failure causation in the seven earliest cases was held in September and October 2011 (“Phase I trial”), and a decision on the dike failure causation issues is expected in the summer of 2012. Plaintiffs in 54 of the 56 remaining cases have agreed to be bound by the Phase I trial record and the court’s decision. The court has granted a temporary stay of proceedings in these cases pending the decision.

TVA has received several notices of intent to sue under various environmental statutes from both individuals and environmental groups, but no such suits have been filed.
 
Civil Penalty and Natural Resource Damages for the Kingston Ash Spill.  In June 2010, TDEC issued a civil penalty order of approximately $12 million to TVA for the Kingston ash spill, citing violations of the Tennessee Solid Waste Disposal Act and the Tennessee Water Quality Control Act.  Of the $12 million, TVA has satisfied $10 million, and TDEC has approved environmental projects valued at $2 million as a credit against the penalty amount.  In January 2011, TVA entered into a memorandum of agreement with TDEC and the U.S. Fish and Wildlife Service establishing a process and a method for resolving the natural resource damage claim associated with the Kingston ash spill.  As part of this memorandum of agreement, TVA agreed to pay $250 thousand each year for three years as a down payment on the amount of natural resource damages ultimately established, and to reimburse TDEC and the U.S. Fish and Wildlife Service for their costs.
 
Case Involving Tennessee Valley Authority Retirement System.  In March 2010, eight current and former participants in and beneficiaries of the Tennessee Valley Authority Retirement System ("TVARS") filed suit in the United States District Court for the Middle District of Tennessee against the six then-current members of the TVARS Board of Directors ("TVARS Board").  The lawsuit challenged the TVARS Board's decision to suspend the TVA contribution requirements for 2010 through 2013, and to amend the TVARS Rules and Regulations to (1) reduce the calculation for cost of living adjustment ("COLA") benefits for CY 2010 through CY 2013, (2) reduce the interest crediting rate for the fixed fund accounts, and (3) increase the eligibility age to receive COLAs from age 55 to 60.  The plaintiffs allege that these actions violated the TVARS Board members' fiduciary duties to the plaintiffs (and the purported class) and the plaintiffs' contractual rights, among other claims.  The plaintiffs sought, among other things, unspecified damages, an order directing the TVARS Board to rescind the amendments, and the appointment of a seventh TVARS Board member.  Five of the six individual defendants filed motions to dismiss the lawsuit, while the remaining defendant filed an answer to the complaint.  In July 2010, TVA moved to intervene in the suit in the event it was not dismissed.  In September 2010, the district court dismissed the breach of fiduciary duty claim against the directors without prejudice, allowing the plaintiffs to file an amended complaint within 14 days against TVARS and TVA but not the individual directors.  The plaintiffs previously had voluntarily withdrawn their constitutional claims, so the court also dismissed those claims without prejudice.  The court dismissed with prejudice the plaintiffs' claims for breach of contract, violation of the Internal Revenue Code, and appointment of a seventh TVARS Board member. 
 
In September 2010, the plaintiffs filed an amended complaint against TVARS and TVA.  The plaintiffs allege, among other things, violations of their constitutional rights (due process, equal protection, and property rights), violations of the Administrative Procedure Act, and breach of statutory duties owed to the plaintiffs.  They seek a declaratory judgment and appropriate relief for the alleged statutory and constitutional violations and breaches of duty.  TVA filed its answer to the amended complaint in December 2010.  In May 2012, the court granted the parties' joint motion to administratively close the case subject to reopening to allow the parties the opportunity to engage in mediation that will likely take a significant amount of time to complete. The parties have agreed to a mediator and are proceeding with mediation.
 
Case Arising out of Hurricane Katrina.  In April 2006, TVA was added as a defendant to a class action lawsuit brought in the United States District Court for the Southern District of Mississippi by 14 Mississippi residents allegedly injured by Hurricane Katrina.  The plaintiffs sued seven large oil companies and an oil company trade association, three large chemical companies and a chemical trade association, and 31 large companies involved in the mining and/or burning of coal, alleging that the defendants' GHG emissions contributed to global warming and were a proximate and direct cause of Hurricane Katrina's increased destructive force.  Action by the United States Supreme Court in January 2011 ended this case in a manner favorable to TVA.
 
However, in May 2011, under a Mississippi state statute that permits the re-filing of lawsuits that were dismissed on procedural grounds, the plaintiffs filed another lawsuit in the United States District Court for the Southern District of Mississippi against the same and additional defendants, again alleging that the defendants' GHG emissions contributed to global warming and were a proximate and direct cause of Hurricane Katrina's increased destructive force. The court dismissed the lawsuit in March 2012 for a variety of reasons, including that the lawsuit presented a non-justiciable political question and that all of the claims were preempted by the CAA. The plaintiffs have appealed the dismissal to the United States Court of Appeals for the Fifth Circuit.
 
Global Warming Cases, Southern District of New York.  In July 2004, two lawsuits were filed in the United States District Court for the Southern District of New York against TVA and other companies that generate power from fossil-fuel electric generating facilities. The plaintiffs alleged that carbon dioxide ("CO2") emissions from such facilities should be ordered abated because they contributed to global warming.  In September 2005, the district court dismissed both lawsuits because they raised political questions that should not be decided by the courts.  Following appellate proceedings, the United States Supreme Court issued a decision in June 2011 that any federal common law cause of action was displaced by the CAA and its implementing regulations. The Supreme Court did not address the plaintiffs' state law claims, but instead remanded the case. The district court entered orders in December 2011 dismissing the federal common law claims in both lawsuits. In December 2011, the plaintiffs voluntarily dismissed the state law claims, ending the lawsuits in a manner favorable to TVA.

Case Regarding Bellefonte Nuclear Plant Units 1 and 2.  In March 2009, in response to a request by TVA, the Nuclear Regulatory Commission ("NRC") reinstated the construction permits for Bellefonte Nuclear Plant ("Bellefonte") Units 1 and 2.  In March 2009 and 2010, Blue Ridge Environmental Defense League (“BREDL”) filed petitions in the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) challenging the NRC's authority to reinstate the construction permits. TVA asked to participate and was granted intervenor status in the cases. In July 2010, the D.C. Circuit consolidated the two BREDL petitions and stayed the combined proceeding pending the conclusion of an administrative proceeding which raised several contentions regarding the reinstatement, including some related to NRC's legal authority to reinstate the permits.  The administrative proceeding was completed in September 2010, with the dismissal of all of BREDL's contentions.  The D.C. Circuit returned the cases to the court's active docket and decided in February 2012 that BREDL's petitions failed to properly challenge the NRC's final orders reinstating the construction permits, and dismissed the petitions for lack of jurisdiction.
 
Administrative Proceedings Regarding Bellefonte Units 3 and 4.  TVA submitted its combined construction and operating license application ("CCOLA") for two Advanced Passive 1000 reactors at Bellefonte Units 3 and 4 to the NRC in October 2007.  In June 2008, Bellefonte Efficiency and Sustainability Team (“BEST”), BREDL, and Southern Alliance for Clean Energy (“SACE”) submitted a joint petition for intervention and a request for a hearing.   The Atomic Safety and Licensing Board ("ASLB") denied standing to BEST and admitted four of the 20 contentions submitted by BREDL and SACE.  The NRC reversed the ASLB's decision to admit two of the four contentions, leaving only two contentions (concerning the estimated costs of the new nuclear plant and the impact of the facility's operations on aquatic ecology) to be litigated in a future hearing.   In January 2012, TVA notified the ASLB that the NRC had placed the CCOLA in “suspended” status indefinitely at TVA's request, and TVA requested that the ASLB hold the proceeding in abeyance pending a decision by TVA regarding the best path forward with regards to the CCOLA.
 
In August 2011, BREDL and SACE petitioned for the admission of a new, late-filed contention to require the environmental analysis completed for the CCOLA to consider the findings of the NRC's Near-Term Task Force regarding the events at the Fukushima Daiichi Nuclear Power Plant ("Fukushima Daiichi").  TVA opposed this petition on the grounds it did not satisfy the standards for non-timely contentions or the standards for admitting a new contention.  In November 2011, the ASLB determined that the proposed contention failed to meet the standards for admission of a new contention in the proceeding.
 
Administrative Proceedings Regarding Watts Bar Nuclear Plant Unit 2.  In July 2009, SACE, the Tennessee Environmental Council, the Sierra Club, We the People, and BREDL filed a request for a hearing and petition to intervene in the NRC administrative process reviewing TVA's application for an operating license for Watts Bar Unit 2. In November 2009, the ASLB granted SACE's request for hearing, admitted two of SACE's seven contentions for hearing, and denied the request for hearing submitted on behalf of the other four petitioners.  The ASLB subsequently dismissed one contention, leaving one aquatic impact contention.  In November 2011, TVA filed a motion for summary disposition, arguing that additional aquatic studies conducted by TVA indicate there is no longer a genuine issue of material fact in connection with SACE's remaining aquatic impact contention.  SACE and the NRC staff filed their answers to the motion in December 2011; SACE opposed TVA's motion while the NRC staff supported it.  In March 2012, the ASLB denied TVA's motion, and TVA anticipates that a hearing on the matter will likely be held in 2013. 

In August 2011, SACE petitioned for the admission of a new, late-filed contention similar to that filed in the Bellefonte Units 3 and 4 proceeding to require an environmental analysis be completed for TVA's operating license application to consider the findings of the NRC's Near-Term Task Force regarding the events at the Fukushima Daiichi reactors.  TVA submitted a reply brief in September 2011 opposing the petition because it did not satisfy the standards for non-timely contentions or for admitting a new contention.  In March 2012, the ASLB denied SACE's motion to admit the new contention.

John Sevier Fossil Plant Clean Air Act Permit. On September 20, 2010, the Environmental Integrity Project, the Southern Environmental Law Center, and the Tennessee Environmental Council filed a petition with the EPA, requesting that the EPA Administrator object to the CAA permit issued to TVA for operation of John Sevier. Among other things, the petitioners allege that repair, maintenance, or replacement activities undertaken at John Sevier Unit 3 in 1986 triggered the Prevention of Significant Deterioration (“PSD”) requirements for sulfur dioxide ("SO2") and nitrogen oxides ("NOx") . The CAA permit, issued by TDEC, remains in effect pending the disposition of the petition. The Environmental Agreements should narrow the scope of this proceeding. See Environmental Agreements.

Shawnee Fossil Plant Clean Air Act Permit. On December 16, 2010, the Environmental Integrity Project and the SACE filed a petition with the EPA requesting that the EPA Administrator object to the proposed CAA renewal permit issued to TVA for operations at Shawnee. Among other things, the petitioners allege that repair, maintenance, or replacement undertaken at Shawnee Units 1 and 4 in the 1989-90 period triggered the PSD requirements for SO2 and NOx. The current permit remains in effect pending KDAQ’s finalization of the renewal permit. The Environmental Agreements should narrow the scope of this proceeding. See Environmental Agreements.

Kingston NPDES Permit Appeal.  The Sierra Club filed a challenge to the National Pollutant Discharge Elimination System (“NPDES”) permit issued by Tennessee for the scrubber-gypsum pond discharge at Kingston in November 2009 before the Tennessee Water Quality Control Board (“TWQCB”).  This is the second such challenge nationally.  In addition to its allegation that Tennessee violated the Clean Water Act by failing to set specific limits on certain toxic discharges, the Sierra Club alleges that no discharges from the pond infrastructure should be allowed because zero-discharge scrubbers exist.  TDEC is the defendant in the challenge, and TVA has intervened in support of TDEC's decision to issue the permit.  The matter was set for a hearing before the TWQCB in February 2011 but has since been stayed by agreement of the parties.  The other similar challenge involves an Allegheny Power NPDES permit for its scrubber discharge at a Pennsylvania plant.
 
Bull Run Fossil Plant NPDES Permit Appeal.  SACE and the Tennessee Clean Water Network (“TCWN”) filed a challenge to the NPDES permit for Bull Run Fossil Plant ("Bull Run") in November 2010.  TDEC is the defendant in the challenge and TVA's motion to intervene to support TDEC's decision to issue the permit was granted in January 2011.  The parties are awaiting a decision on the petitioners' motion for summary judgment.
 
Johnsonville Fossil Plant NPDES Permit Appeal.  SACE and TCWN filed a challenge to the NPDES permit for Johnsonville in March 2011.  TDEC is the defendant in the challenge.  TVA's motion to intervene was granted in August 2011. The matter has not yet been given a hearing date before the TWQCB.
 
John Sevier Fossil Plant NPDES Permit Appeal.  SACE and TCWN filed a challenge to the NPDES permit for John Sevier in May 2011.  TDEC is the defendant in the challenge.  TVA's motion to intervene was granted in August 2011. The matter has not yet been given a hearing date before the TWQCB.
 
Gallatin Fossil Plant NPDES Permit Appeal. SACE, TCWN, and the Sierra Club filed a challenge to the NPDES permit for Gallatin Fossil Plant ("Gallatin") in June 2012. TDEC is the defendant in the challenge. TVA anticipates filing a motion to intervene to support TDEC's decision to issue the permit.

Information Request from the EPA.  In April 2008, TVA received a request from the EPA under Section 114 of the CAA requesting extensive information about maintenance, repair, and replacement projects at and the operations of 14 coal-fired units. The Environmental Agreements have resolved most issues related to this information request, excluding claims related to sulfuric acid mist.  See Environmental Agreements.
 
Petitions Resulting from Japanese Nuclear Events. As a result of the March 2011 Japanese nuclear events, petitions have been filed with the NRC which could impact TVA's nuclear program. While some petitions have been dismissed after review, petitions that remain open include the following:
 
Petition to Immediately Suspend the Operating Licenses of GE BWR Mark I Units Pending the Full NRC Review With Independent Expert and Public Participation From Affected Emergency Planning Zone Communities
 
Beyond Nuclear filed a petition in April 2011, requesting that the NRC take emergency enforcement action against all nuclear reactor licensees that operate units that use the General Electric Mark I BWR design. TVA uses this design at Browns Ferry Nuclear Plant ("Browns Ferry") Units 1, 2, and 3. The petition requests the NRC to take several actions, including the suspension of the operating licenses at the affected nuclear units, including Browns Ferry, until several milestones have been met. In December 2011, the NRC provided its initial response to the petition. The NRC accepted five specific requests that would apply directly or indirectly to Browns Ferry, including issues relating to spent fuel pool use and location, Mark I containment hardened vent systems and design, and backup electrical power. Each of these items was accepted for further investigation, but the requests for immediate action were rejected. In April 2012, and the petitioner was informed by the NRC that the proposed Director's Decision regarding the petition had been extended to January 2013.
 
Twelve separate petitions on various issues
 
In August 2011, the Natural Resources Defense Council submitted twelve separate letters to the NRC requesting action on various health and safety aspects of operating nuclear facilities in the United States. The NRC is treating these as a single 2.206 Petition. In April 2012, the petitioner was informed by the NRC that its evaluation of the petition had been extended until January 2013.
 
Petition Pursuant to 10 CFR 2.206 - Demand For Information Regarding Compliance with 10 CFR 50, Appendix A, General Design Criterion 44, Cooling Water, and 10 CFR 50.49, Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power Plants
 
A petition was filed by the Union of Concerned Scientists in July 2011, requesting that a demand for information be issued for affected licensees, including TVA with regards to Browns Ferry, to describe how the facilities comply with General Design Criterion 44, Cooling Water, within Appendix A to 10 CFR Part 50, and with 10 CFR 50.49, Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power Plants, for all applicable design and licensing bases events. In February 2012, the petitioner was informed by the NRC that the proposed Director's Decision regarding the petition had been extended to January 2013.

Case Involving the NRC Waste Confidence Decision on Spent Nuclear Fuel Storage. In June 2012, the D.C. Circuit vacated the NRC's updated Waste Confidence Decision (“WCD”). The WCD is a generic determination by the NRC that spent nuclear fuel can be safely managed until a permanent off-site repository is established and has been a key component of NRC licensing activities since 1984. The most recent update provided that the permanent repository would be available when necessary and that spent fuel could be stored for 60 years after a plant's license terminated. The D.C. Circuit vacated this update on the grounds that, among other things, the NRC failed to support it with an adequate National Environmental Policy Act ("NEPA") review and the NRC did not evaluate what would happen if the repository was never built.

In June 2012, multiple intervenor groups submitted a petition to the NRC to (a) hold in abeyance all pending reactor licensing decisions that would depend upon the WCD and (b) establish a process for ensuring that the remanded proceeding complies with the public participation requirements of Section 189a of the Atomic Energy Act. TVA will file its answer to the petition in August 2012.