Kingston Fossil Plant Ash Spill
3 Months Ended
Dec. 31, 2013
Environmental Remediation Obligations [Abstract]  
Kingston Fossil Plant Ash Spill
Kingston Fossil Plant Ash Spill

The Event

In December 2008, one of the dredge cells at the Kingston Fossil Plant ("Kingston") failed, and over five million cubic yards of water and coal fly ash flowed out of the cell. TVA is continuing cleanup and recovery efforts in conjunction with federal and state agencies.  TVA completed the removal of time-critical ash from the river during the third quarter of 2010.  In November 2012, the Environmental Protection Agency ("EPA") and the Tennessee Department of Environment and Conservation ("TDEC") approved a plan to allow the Emory River's natural processes to remediate the remaining ash in the river, and to conduct a long-term monitoring program. TVA estimates that the physical cleanup work (final cleanup work and closure) will be completed in the spring of 2015.  A final assessment, issuance of a completion report, and approval by the State of Tennessee and the EPA are expected to occur by the third quarter of 2015.  

Claims and Litigation

See Note 18Legal ProceedingsLegal Proceedings Related to the Kingston Ash Spill and Civil Penalty and Natural Resource Damages for the Kingston Ash Spill.

Financial Impact

Because of the uncertainty at this time of the final costs to complete the work prescribed by the ash disposal plan, a range of reasonable estimates has been developed by cost category.  Known amounts, most likely scenarios, or the low end of the range for each category have been accumulated and evaluated to determine the total estimate.  The range of costs varies from approximately $1.1 billion to approximately $1.2 billion.

TVA recorded an estimate of $1.1 billion for the cost of cleanup related to this event.  In August 2009, TVA began using regulatory accounting treatment to defer all actual costs already incurred and expected future costs related to the ash spill.  The cost is being charged to expense as it is collected in rates over 15 years, beginning October 1, 2009.  As the estimate changes, additional costs may be deferred and charged to expense prospectively as they are collected in future rates.

As work continues to progress and more information is available, TVA will review its estimates and revise them as appropriate.  TVA has accrued a portion of the estimated cost in current liabilities, with the remaining portion shown as a long-term liability on TVA's consolidated balance sheets.  Amounts spent since the event through December 31, 2013, totaled $978 million.  The remaining estimated liability at December 31, 2013, was $147 million.

TVA has not included the following categories of costs in the above estimate since it has been determined that these costs are currently either not probable or not reasonably estimable: penalties (other than the penalties set out in a June 2010 TDEC order), regulatory directives, natural resources damages (other than payments required under a memorandum of agreement with TDEC and the U.S. Fish and Wildlife Service establishing a process and a method for resolving the natural resource damages claim), future lawsuits, future claims, long-term environmental impact costs, final long-term disposition of the ash processing area, and costs associated with new laws and regulations.  There are certain other costs that will be incurred that have not been included in the estimate as they are appropriately accounted for in other areas of the consolidated financial statements.  Associated capital asset purchases are recorded in property, plant, and equipment.  Ash handling and disposition costs from current plant operations are recorded in operating expenses.  A portion of the dredge cell closure costs are also excluded from the estimate, as they are included in the non-nuclear asset retirement obligations ("ARO") liability.

Insurance

TVA had property and excess liability insurance programs in place at the time of the Kingston ash spill.  TVA pursued claims under both the property and excess liability programs and has settled all of its property insurance claims and some of its excess liability insurance claims.  In April 2012, TVA initiated arbitration proceedings against the remaining three excess liability insurance companies in accordance with the policies’ dispute resolution provisions. TVA has successfully resolved two of these proceedings and is pursuing the third, which is scheduled to begin in June 2014. TVA is seeking recovery of certain costs incurred in the cleanup project, including the costs of removing ash from property or waters owned by the State of Tennessee, and related expenses. TVA has received insurance proceeds of $242 million, of which $150 million was received in the first quarter of 2014. The insurance proceeds are being recorded as reductions to the regulatory asset and will reduce amounts collected in future rates. TVA has also received $11 million in interest related to certain insurance proceeds.