XML 471 R25.htm IDEA: XBRL DOCUMENT v3.24.0.1
Property, plant and equipment
12 Months Ended
Dec. 31, 2023
Property, plant and equipment [abstract]  
Property, plant and equipment 13 Property, plant and equipment
Recognition and measurement
Property, plant and equipment is stated at cost, as defined in IAS 16 “Property, Plant and Equipment”, less accumulated depreciation and
accumulated impairment losses. The cost of property, plant and equipment includes, where applicable, the estimated close-down and restoration
costs associated with the asset.
Property, plant and equipment includes right-of-use assets arising from leasing arrangements, shown separately from owned and leasehold assets.
Once an undeveloped mining project has been determined as commercially viable and approval to mine has been given, further expenditure is
capitalised under “capital work in progress” together with any amount transferred from “Exploration and evaluation”. Once the project enters into an
operation phase, the amounts capitalised in capital work in progress are reclassified to their respective asset categories.
Costs incurred while commissioning new assets, in the period before they are capable of operating in the manner intended by management, are
capitalised unless associated with pre-production revenue. Development costs incurred after the commencement of production are capitalised to the
extent they are expected to give rise to a future economic benefit. Interest on borrowings related to construction or development projects is
capitalised, at the rate payable on project-specific debt if applicable or at the Group or subsidiary’s cost of borrowing if not. This is performed until
the point when substantially all the activities that are necessary to make the asset ready for its intended use are complete. It may be appropriate to
use a subsidiary’s cost of borrowing when the debt was negotiated based on the financing requirements of that subsidiary.
Depreciation of non-current assets
Property, plant and equipment is depreciated over its useful life, or over the remaining life of the mine, smelter or refinery if that is shorter and there
is no reasonable alternative use for the asset by the Group. Depreciation commences when an asset is available for use and therefore there is no
depreciation for capital work in progress.
Straight line basis
Assets within operations for which production is not expected to fluctuate significantly from one year to another or which have a physical life shorter
than the related mine are depreciated on a straight line basis as follows:
Type of Property, plant and equipment
Land and buildings
Plant and equipment
Land
Buildings
Power-generating assets
Other plant and equipment
Depreciation profile
Not depreciated
5 to 50 years
See Power note below
on page 195
3 to 50 years
The useful lives and residual values for material assets and categories of assets are reviewed annually and changes are reflected prospectively.
Units of production basis
For mining properties and leases and certain mining equipment, consumption of the economic benefits of the asset is linked to production. Except
as noted below, these assets are depreciated on the units of production basis.
In applying the units of production method, depreciation is normally calculated based on production in the period as a percentage of total expected
production in current and future periods based on mineral reserves and, for some mines, other mineral resources. Other mineral resources may be
included in the calculations of total expected production in limited circumstances where there are very large areas of contiguous mineralisation, for
which the economic viability is not sensitive to likely variations in grade, as may be the case for certain iron ore, bauxite and industrial mineral
deposits, and where there is a high degree of confidence that the other mineral resources can be extracted economically. This would be the case
when the other mineral resources do not yet have the status of ore reserves merely because the necessary detailed evaluation work has not yet
been performed and the responsible technical personnel agree that inclusion of a proportion of measured and indicated resources in the calculation
of total expected production is appropriate based on historical reserve conversion rates. 
The required level of confidence is unlikely to exist for minerals that are typically found in low-grade ore (as compared with the above), such as
copper or gold. In these cases, specific areas of mineralisation have to be evaluated in detail before their economic status can be predicted with
confidence.
Sometimes the calculation of depreciation for infrastructure assets, primarily rail and port, considers measured and indicated resources. This is
because the asset can benefit current and future mines. The measured and indicated resource may relate to mines which are currently in production
or to mines where there is a high degree of confidence that they will be brought into production in the future. The quantum of mineral resources is
determined taking into account future capital costs as required by the JORC code. The depreciation calculation, however, applies to current mines
only and does not take into account future development costs for mines which are not yet in production. Measured and indicated resources are
currently incorporated into depreciation calculations in the Group’s Australian iron ore business.
13 Property, plant and equipment continued
Key judgement - estimation of asset lives
The useful lives of the major assets of a cash-generating unit are often dependent on the life of the orebody to which they relate. Where this is
the case, the lives of mining properties, and their associated refineries, concentrators and other long-lived processing equipment are generally
limited to the expected life of the orebody. The life of the orebody, in turn, is estimated on the basis of the life-of-mine plan. Where the major
assets of a cash-generating unit are not dependent on the life of a related orebody, management applies judgement in estimating the
remaining service potential of long-lived assets. Factors affecting the remaining service potential of smelters include, for example, smelter
technology and electricity purchase contracts when power is not sourced from the Group, or in some cases from local governments permitting
electricity generation from hydropower stations.
Impact of climate change on our business - estimation of asset lives
We expect there to be a higher demand for copper, aluminium, lithium and high-grade iron ore in order to meet demand for the minerals
required to transition to a low carbon economic environment, consistent with the climate change commitments of the Paris Agreement. We
expect this to exceed new supply to the market and therefore increase prices. Under the Aspirational Leadership scenario, the economic cut-
off grade for our Mineral Reserves is expected to be lower; in effect we would mine a greater volume of material before the mines are
depleted. We cannot quantify the difference this would make without undue cost as it would require revised mine plans, but for property, plant
and equipment this increased volume of material would reduce the depreciation charge during any given period for assets that use the “Units
of production” depreciation basis.
Deferred stripping
In open pit mining operations, overburden and other waste materials must be removed to access ore from which minerals can be extracted
economically. The process of removing overburden and other waste materials is referred to as stripping. During the development of a mine (or, in
some instances, pit; see below), before production commences, stripping costs related to a component of an orebody are capitalised as part of the
cost of construction of the mine (or pit). These are then amortised over the life of the mine (or pit) on a units of production basis.
Where a mine operates several open pits that are regarded as separate operations for the purpose of mine planning, initial stripping costs are
accounted for separately by reference to the ore from each separate pit. If, however, the pits are highly integrated for the purpose of mine planning,
the second and subsequent pits are regarded as extensions of the first pit in accounting for stripping costs. In such cases, the initial stripping of the
second and subsequent pits is considered to be production phase stripping (see below).
Key judgement - deferral of stripping costs
We apply judgement as to whether multiple pits at a mine are considered separate or integrated operations. This determines whether the
stripping activities of a pit are classified as pre-production or production phase stripping and, therefore, the amortisation base for those costs.
The analysis depends on each mine’s specific circumstances and requires judgement: another mining company could make a different
judgement even when the fact pattern appears to be similar.
The following factors would point towards the initial stripping costs for the individual pits being accounted for separately:
if mining of the second and subsequent pits is conducted consecutively following that of the first pit, rather than concurrently;
if separate investment decisions are made to develop each pit, rather than a single investment decision being made at the outset;
if the pits are operated as separate units in terms of mine planning and the sequencing of overburden removal and ore mining, rather than
as an integrated unit;
if expenditures for additional infrastructure to support the second and subsequent pits are relatively large; and
if the pits extract ore from separate and distinct orebodies, rather than from a single orebody.
If the designs of the second and subsequent pits are significantly influenced by opportunities to optimise output from several pits combined,
including the co-treatment or blending of the output from the pits, then this would point to treatment as an integrated operation for the
purposes of accounting for initial stripping costs. The relative importance of each of the above factors is considered in each case.
In order for production phase stripping costs to qualify for capitalisation as a stripping activity asset, three criteria must be met:
it must be probable that there will be an economic benefit in a future accounting period because the stripping activity has improved access
to the orebody;
it must be possible to identify the “component” of the orebody for which access has been improved; and
it must be possible to reliably measure the costs that relate to the stripping activity.
A “component” is a specific section of the orebody that is made more accessible by the stripping activity. It will typically be a subset of the
larger orebody that is distinguished by a separate useful economic life (for example, a pushback).
Recognition and measurement of deferred stripping
Phase
Development Phase
Production Phase
Stripping activity
Overburden and other waste removal during
the development of a mine before production
commences.
Production phase stripping can give access to two benefits: the extraction of ore in the
current period and improved access to ore which will be extracted in future periods.
Period of benefit
After commissioning of the mine.
Future periods after first phase is complete.
Current and future benefit are
indistinguishable.
Capitalised to mining
properties and leases in
property, plant and
equipment
During the development of a mine, stripping
costs relating to a component of an orebody
are capitalised as part of the cost of
construction of the mine.
It may be the case that subsequent phases
of stripping will access additional ore and
that these subsequent phases are only
possible after the first phase has taken
place. Where applicable, the Group
considers this on a mine-by-mine basis.
Generally, the only ore attributed to the
stripping activity asset for the purposes of
calculating the life-of-component ratio is the
ore to be extracted from the originally
identified component.
Stripping costs for the component are
deferred to the extent that the current period
ratio exceeds the life-of-component ratio.
Allocation to inventory
Not applicable
Not applicable
The stripping cost is allocated to inventory
based on a relevant production measure
using a life-of-component strip ratio. The
ratio divides the tonnage of waste mined for
the component for the period either by the
quantity of ore mined for the component or
by the quantity of minerals contained in the
ore mined for the component. In some
operations, the quantity of ore is a more
appropriate basis for allocating costs,
particularly when there are significant by-
products.
Component
A “component” is a specific section of the orebody that is made more accessible by the stripping activity. It will typically be a subset of the
larger orebody that is distinguished by a separate useful economic life (for example, a pushback).
Life-of-component ratio
The life-of-component ratios are based on the mineral reserves of the mine (and for some mines, other mineral resources) and the annual
mine plan; they are a function of the mine design and, therefore, changes to that design will generally result in changes to the ratios.
Changes in other technical or economic parameters that impact the mineral reserves (and for some mines, other mineral resources) may
also have an impact on the life-of-component ratios even if they do not affect the mine design. Changes to the ratios are accounted for
prospectively.
Depreciation basis
Depreciated on a “units of production” basis based on expected production of either ore or minerals contained in the ore over the life of the
component unless another method is more appropriate.
Property, plant and equipment - owned and leased assets
2023
US$m
2022
US$m
Property, plant and equipment – owned
65,290
63,731
Right-of-use assets – leased
1,178
1,003
Net book value
66,468
64,734
13 Property, plant and equipment continued
Property, plant and equipment – owned
2023
Note
Mining
properties
and leases(a)
US$m
Land
and
buildings
US$m
Plant
and
equipment
US$m
Capital
works in
progress
US$m
Total
US$m
Net book value
At 1 January 2023
10,529
6,699
34,407
12,096
63,731
Adjustment on currency translation(b)
14
116
495
54
679
Adjustments to capitalised closure costs
14
(292)
(292)
Interest capitalised(c)
9
275
275
Additions(d)
222
207
1,381
5,110
6,920
Depreciation for the year(a)
(802)
(504)
(3,511)
(4,817)
Impairment charges(e)
(92)
(58)
(922)
(87)
(1,159)
Disposals
(28)
(73)
(27)
(128)
Transfers and other movements(f)
3,976
1,590
4,568
(10,053)
81
At 31 December 2023
13,555
8,022
36,345
7,368
65,290
Balance sheet analysis
– cost
29,731
14,737
80,993
7,728
133,189
– accumulated depreciation and impairment
(16,176)
(6,715)
(44,648)
(360)
(67,899)
Non-current assets pledged as security(g)
5,307
1,477
6,980
3,715
17,479
2022
Note
Mining
properties
and leases(a)
US$m
Land
and
buildings
US$m
Plant
and
equipment
US$m
Capital
works in
progress
US$m
Total
US$m
Net book value
At 1 January 2022
10,817
5,995
33,453
13,528
63,793
Adjustment on currency translation(b)
(436)
(344)
(1,870)
(311)
(2,961)
Adjustments to capitalised closure costs
14
520
520
Interest capitalised(c)
9
416
416
Additions(d)
360
304
1,111
4,732
6,507
Depreciation for the year(a)
(891)
(433)
(3,171)
(4,495)
Disposals
(3)
(1)
(38)
(4)
(46)
Newly consolidated operations(h)
1
5
6
Transfers and other movements(f)
162
1,177
4,922
(6,270)
(9)
At 31 December 2022
10,529
6,699
34,407
12,096
63,731
Balance sheet analysis
– cost
25,263
12,805
74,562
13,118
125,748
– accumulated depreciation and impairment
(14,734)
(6,106)
(40,155)
(1,022)
(62,017)
Non-current assets pledged as security(g)
1,602
491
5,113
8,876
16,082
(a)At 31 December 2023, the net book value of capitalised production phase stripping costs totalled US$2,505 million, with US$2,069 million within “Property, plant and equipment” and a further
US$436 million within “Investments in equity accounted units” (2022: total of US$2,497 million, with US$2,038 million in “Property, plant and equipment” and a further US$460 million within
“Investments in equity accounted units”). During the year, capitalisation of US$325 million was partly offset by depreciation of US$324 million, inclusive of amounts recorded within equity
accounted units (2022: US$411 million offset by depreciation of US$331 million). Depreciation of deferred stripping costs in respect of subsidiaries of US$216 million (2022: US$246 million;
2021: US$201 million) is included within “Depreciation for the year”.
(b)Adjustment on currency translation represents the impact of exchange differences arising on the translation of the assets of entities with functional currencies other than the US dollar, recognised
directly in the currency translation reserve. The adjustment in 2023 arose primarily from the strengthening of the Australian and Canadian dollars against the US dollar.
(c)Our average borrowing rate, excluding any project finance, used for capitalisation of interest is 7.50% (2022: 5.60%).
(d)Additions to “Property, plant and equipment” includes US$94 million of spend on carbon abatement (2022: US$86 million).
(e)In 2023, the impairment charges related primarily to our alumina refineries in the Aluminium segment. Refer to note 4 for details.
(f)“Transfers and other movements” includes reclassification between categories.
(g)Excludes assets held under capitalised lease arrangements. Non-current assets pledged as security represent amounts pledged as collateral against US$3,994 million (2022: US$3,965 million)
of loans, which are included in note 20.
(h)In 2022, the acquisition relates to our purchase of Rincon, a lithium project in Argentina. Refer to note 5 for details.
Impact of climate change on our business - useful economic lives of our power generating assets
The Group has committed to reducing Scope 1 and Scope 2 carbon emissions by 50% relative to our 2018 baseline by 2030 and achieving
net zero emission across our operations by 2050. We expect to invest US$5 billion to US$6 billion on carbon abatement projects between
2022 and 2030 (revised from US$7.5 billion in prior year). Transitioning electricity from principally fossil fuel-based power generating assets to
principally renewables is critical to achieving that goal. The carrying value of power generating assets is set out in the table below. The
weighted average remaining useful economic life of plant and equipment for fossil fuel-based power generating assets is 10 years (2022: 13
years). Given the technical limitations of intermittent renewable energy generation and energy storage systems, and our need for reliable
baseload electricity, we expect our current generation assets will be integral to those needs for the foreseeable future. We are investing in
research and development and evaluating new market options that may overcome these technical challenges. Should pathways for
eliminating fossil fuel power generating assets be identified we may need to accelerate depreciation or impair the assets; however, at this
present moment the requirement for fossil fuel powered back-up means that early retirement of the assets is not expected and no change to
depreciation rates is required.
2023
2022
Net book value
Land
and
buildings
US$m
Plant
and
equipment
US$m
Land
and
buildings
US$m
Plant
and
equipment
US$m
Fossil fuels
87
932
25
882
Renewables(a)
201
2,456
198
2,352
(a)The increase of US$104 million in renewables plant & equipment is primarily attributable to the Quebec power stations which are essential to the production of hydroelectricity for the
manufacture of low-carbon aluminium in our newly expanded facility at Complexe Jonquière in Saguenay-Lac-Saint-Jean, as well as the Kemano hydropower station which continues to
ensure the long-term, sustainable production of low-carbon aluminium at our smelter in Kitimat. Both assets are items of property, plant and equipment which are owned by Rio Tinto.
Right-of-use assets – leased
2023
2022
Land and buildings
US$m
Plant and equipment
US$m
Total
US$m
Land and buildings
US$m
Plant and equipment
US$m
Total
US$m
Net book value
At 1 January
515
488
1,003
549
585
1,134
Adjustment on currency translation
11
4
15
(35)
(16)
(51)
Additions
96
420
516
49
254
303
Depreciation for the year
(88)
(305)
(393)
(61)
(295)
(356)
Impairment charges(a)
(1)
(7)
(8)
Disposals
(1)
(1)
Transfers and other movements
10
36
46
13
(40)
(27)
At 31 December
543
635
1,178
515
488
1,003
(a)In 2023, the impairment charges related to our alumina refineries in the Aluminium segment. Refer to note 4 for details.
The leased assets of the Group include land and buildings (mainly office buildings) and plant and equipment, the majority of which are marine
vessels. Lease terms are negotiated on an individual basis and contain a wide range of terms and conditions. Right-of-use assets are depreciated
on a straight line basis over the life of the lease, taking into account any extensions that are likely to be exercised.