As stated in our Company's public disclosure dated 18.05.2023, it was publicly disclosed that our pre-license application for a total capacity of 500 MW (200 MW Keberli SPP, 200 MW Güzelkuyu SPP and 100 MW Kızılağaç WPP), including 400 MW SPP and 100 MW WPP, for storage generation facilities through Sarı Perakende Enerji Satış ve Tic. A.Ş, a 100% subsidiary of our Company, was accepted.
In this process, revisions were made to the Keberli SPP and Güzelkuyu SPP project site coordinates of our pre-licensed projects belonging to our Sarı Perakende Enerji Satış ve Tic. A.Ş. company.
Detailed information regarding the field changes are given below :
On 03.08.2023, a project area change application was made to EMRA for the Keberli SPP project area, for which an EIA application was made on 03.08.2023, due to the planning of housing, trade and social reinforcement etc. construction within the scope of the Kahramanmaraş earthquake dated February 6, 2023, in accordance with the letter dated 18.08.2023 and numbered 466747 of the Mass Housing Administration of the Ministry of Environment, Urbanization and Climate Change of the Republic of Turkey. With the board decision dated 08.02.2024 and numbered 12428-6 by EMRA, it was found appropriate to change the district of the production facility from Eyyübiye to Halfeti.
On 08.08.2023, a project site change application was made to EMRA due to the overlap of the Güzelkuyu SPP project area, for which an EIA application was made on 08.08.2023, with the Şanlıurfa OIZ additional area finalized on 16.08.2023, as stated in the letter of the Ministry of Industry and Technology dated 18.08.2023 and numbered 4989435. With the board decision dated 25.01.2024 and numbered 12401-8 by EMRA, it was found appropriate to change the production facility district from Eyyübiye to Halfeti.
We submit for the information of the public.