oda_MaterialEventDisclosureGeneralAbstract|
|
|
||||||||
|
oda_UpdateAnnouncementFlag|
|
|
Evet (Yes)
|
|||||||
|
oda_CorrectionAnnouncementFlag|
|
|
Hayır (No)
|
|||||||
|
oda_DateOfThePreviousNotificationAboutTheSameSubject|
|
|
28.07.2021, 12.08.2021, 16.11.2021, 22.01.2022, 11.03.2022, 24.08.2022, 21.03.2023, 07.12.2023
|
|||||||
|
oda_DelayedAnnouncementFlag|
|
|
Hayır (No)
|
|||||||
|
oda_AnnouncementContentSection|
|
|
||||||||
|
oda_ExplanationSection|
|
|
||||||||
|
oda_ExplanationTextBlock|
|
Today (14.06.2024), 7 MW of the 42.5711 MW Auxiliary Source installed capacity (Hybrid SPP) of our Company's "Taşpınar Combined Renewable Electricity Generation Facility Project", which is under construction in Korubaşı Neighborhood, Nilüfer District, Bursa Province, has been commissioned with the acceptance of the Ministry. With this acceptance, the total installed capacity of the Taşpınar Hybrid SPP has reached 16.4 MW and the first phase of the project has been completed. Construction work on the second and final phase of the project is scheduled to be completed by the end of 2024.
As of today, the total installed capacity of our Taşpınar WPP and Hybrid SPP plant is 95.4 MWm / 73 MWe.
Important developments that may occur in the upcoming period regarding the project will be shared with our investors through annual reports and material event disclosures.
This statement has been translated into English for informational purposes. In the event of any discrepancy between the Turkish and English versions of this disclosure statement, the Turkish version shall prevail.
|
||||||||