We had previously announced that the drilling works of our Geothermal Power Plant investment, which will have the world's most advanced environmental technology and standards, in the license area
owned by Kocaer Energy
in Aydın Kuyucak, were continuing and that the EIA permit process for the "Kocaer 1 GPP" Project to be established had been initiated.
As a result of the engineering studies we carried out in our license area, the need to change the project area has arised and an application
has been made to EMRA for
license amendment. Due to the project site change which we requested in order to increase the benefit of the investment, the current EIA application has been terminated by us and a project site change has been requested from EMRA. Work continues for all necessary permits and regulations
for the new project site
, including EIA, which will be initiated following the approval of EMRA.
Our company aims to expand its activities in the field of renewable energy, which it has determined among its strategic priorities. After the Kocaer GPP 1 power plant investment, which will have a capacity of 24 MW and which we plan to commission in 2026, we aim to meet all of our current electricity needs, reduce our greenhouse gas emissions, and reach a structure that sells a significant part of the energy we produce,
with the electrical energy obtained
together with Kocaer Çelik's rooftop solar power plants.
It is announced to the public with respect.
|
||||||||