As we reported in our PDP statement dated 25.05.2023;
Our subsidiary Progresiva Enerji Yatırımları Tic. A.Ş., was given a Pre-license by the Energy Market Regulatory Authority (EMRA) for 250 MW Wind Power Plant (WPP) and 1000 MWh Electricity Storage Facility (ESF).
Our Site Amendment Application for a different site with a higher wind capacity factor than the project site in our current Pre-license was approved by EMRA.
The new project site is located in Tekirdağ, Süleymanpaşa and Muratlı districts. Measurements have been made in the relevant area for approximately two months with two Wind Measurement Stations, and Environmental Impact Assessment (EIA) and Technical Interaction Analysis (TIA) processes have been initiated.
In the following stages, developments regarding the progress of the project will be shared with the public.