XML 144 R93.htm IDEA: XBRL DOCUMENT v3.22.4
Commitments, Concessions and Contingent Liabilities (Narratives) (Details)
₪ / shares in Units, Numberofpersons in Thousands
1 Months Ended 12 Months Ended
Oct. 31, 2020
₪ / shares
Jun. 30, 2020
USD ($)
Dec. 31, 2022
ILS (₪)
Numberofpersons
Dec. 31, 2022
USD ($)
Numberofpersons
Dec. 31, 2017
USD ($)
Dec. 31, 2016
Dec. 31, 2022
USD ($)
Capital commitments [abstract]              
Contractual commitments for acquisition of raw materials and energy             $ 2,600,000,000
Contractual commitments for acquisition of Property, Plant and Equipment             684,000,000
Project cost to be paid throughout construction and operation period       $ 110,000,000      
Expected extension of construction period     4 years 4 years      
Expected extension of operation period     25 years 25 years      
Total amount of new natural gas agreement with Energean         $ 2,000,000,000    
Year of supply of natural gas         15 years    
Price of gas supply obtained from Energean | ₪ / shares ₪ 4            
Rotem's existing obligations to rehabilitate its mining and plants areas       $ 19,000,000      
Amount of alleged damages for dialogue meeting to be held before pursuing legal action       $ 27,000,000      
Period of mining of phosphate or until exhaustion of raw material whichever occurs first           25 years  
Long term lease agreement with a third party of office building   15 years          
Extension term lease agreement with third party of office building   10 years          
Annual rent on long-term lease agreement   $ 3,000,000          
Indemnification payable for directors and officers limit             300,000,000
Consolidated Depreciation Expenses Relating To Assets In Concession Area             108,000,000
Dsw Rate Of Royalties Payment     5.00% 5.00%      
Royalty rate for production of phosphates     0.05 0.05      
Total royalties       $ 1,500,000      
Claimed remedies for an application for a class action on alleged environmental hazards to Zin stream     ₪ 3,000,000,000       933,000,000
Remedy relating aquifer and Bokek stream restoration - application for certification of a claim as class action             24,000,000
Remedy relating dyke collapse - first class action for 8.68 million persons     ₪ 1,000       311
Number of persons involved in salt harvesting project | Numberofpersons     8,680 8,680      
Remedy relating dyke collapse - second class action     ₪ 250,000,000       77,000,000
Award personal compensation     2,000       622
Remedy relating dyke collapse - third class action     202,500,000       63,000,000
Remedy relating dyke collapse - Nature and Parks Authority     397,000,000       123,000,000
Amount transferred to NPA | ₪     3,000,000        
A class action claim relating air pollution in Haifa Bay     ₪ 13,400,000,000       4,200,000,000
The company's part in financing of the coastline defenses     39.50% 39.50%      
The company's part in financing of the Salt Harvesting project     80.00% 80.00%      
The government's part in financing of the Salt Harvesting project     20.00% 20.00%      
Maximum government's share in financing of the Salt Harvesting project | ₪     ₪ 1,400,000,000        
ICL's damages lawsuit against IBM             300,000,000
IBM counterclaim     170,000,000       53,000,000
Amount of damages alleged by group incurred respondents     133,000,000 $ 40,000,000      
Amount Of additional damages alleged by group incurred respondents     57,000,000 17,000,000      
Maximal damage for Hamonization for application for certification of a claim as class action     426,000,000       121,000,000
Minimal damage for Hamonization for application for certification of a claim as class action     26,000,000       8,000,000
Compensation in application for certification of a claim as class action regarding alleged monopolistic exploitation - difference test     56,000,000       17,000,000
Compensation in application for certification of a claim as class action regarding alleged monopolistic exploitation - comparison test     73,000,000       $ 23,000,000
Compensation amount for restoration expenses, legal expenses and other expenses     ₪ 115,000,000 $ 33,500,000      
Percentage of mining royalties     2.30% 2.30%      
Royalty payment       $ 4,200,000      
Estimated public compensation     ₪ 1,400,000,000 $ 435,000,000