The 6,000 kWe solar power plant, whose final acceptance has been made, on the land in Eşme district of Uşak province belonging to one of our Group Companies, Adaçal Endüstri Mineraller A.Ş., has been commissioned and started to produce electricity. Approximately 14,000 - 14,500 MWh of electricity will be produced on an annual basis in three solar power plants with a total installed inverter power of 8,000 kWe, together with two 2,000 kWe solar power plants previously commissioned by the company, and 53% of the total electricity consumption will be met by electricity produced from solar energy. The investment is also expected to prevent 9,000 tons of carbon emissions.
With the commissioning of the mentioned facility, 27 MW part of the 44 MW call letter owned by Bera Holding Group Companies has been commissioned and completed with an investment amount of approximately 15.5 million USD. The remaining 17 MW is planned to be commissioned by the end of 2025.
Respectfully announced to the public.
This statement has also been explained in Turkish, and in case of any differences in the explanation texts the Turkish explanation will be taken as basis.
|
||||||||