In our Material Event Disclosure dated June 12, 2025, it was announced to the public that our group companies had signed installation agreements with SYS Enerji San. ve Tic. A.Ş. for the establishment of Solar Power Plants (SPPs) as follows:
Divapan Entegre Agaç Panel Sanayi Ticaret A.S. – for the installation of a 999 kWe capacity plant on the land located in Konya Province, Meram District, Karahüyük Neighborhood, Block 27559, Parcel 68, at a cost of USD 571,669.56,
MPG Makine Prodüksiyon Grubu Makine Imalat Sanayi ve Ticaret A.S. – for the installation of a 400 kWe capacity plant on the land located in Konya Province, Meram District, Karahuyuk Neighborhood, Block 27559, Parcel 66, at a cost of USD 208,551.42.
The facilities, with a total installed capacity of 1,300 kWe, have been completed, commissioned, and commenced electricity generation.