[CONSOLIDATION_METHOD_TITLE] [CONSOLIDATION_METHOD]
Related Companies
[]
Related Funds
[]
English
oda_MaterialEventDisclosureGeneralAbstract|
Material Event Disclosure General
oda_UpdateAnnouncementFlag|
Update Notification Flag
Hayır (No)
oda_CorrectionAnnouncementFlag|
Correction Notification Flag
Hayır (No)
oda_DateOfThePreviousNotificationAboutTheSameSubject|
Date Of The Previous Notification About The Same Subject
19.03.2024, 16.05.2025
oda_DelayedAnnouncementFlag|
Postponed Notification Flag
Hayır (No)
oda_AnnouncementContentSection|
Announcement Content
oda_ExplanationSection|
Explanations
oda_ExplanationTextBlock|
The Ministry of Environment, Urbanization, and Climate Change has issued an "Environmental Impact Assessment Positive" decision for the Amasya Wind Energy Plant (30 MWm / 30 MWe) and Electricity Storage Facility (30 MWe / 60 MWh) project, which is planned to be built in the Amasya Province by our wholly-owned subsidiary, Akfen Elektrik Enerjisi Toptan Satış A.Ş.

This EIA positive decision is the fifth one for our total 310 MW capacity 6 electricity storage projects with solar and wind power generation, which are part of our second-phase investments, as outlined in our 3-year investment program and presentation announced on 19.03.2024 via Public Disclosure Platform.

As stated in our announcement on 16.05.2025, once our first-phase investments, whose construction processes are ongoing, are completed in 2025, our total installed capacity will be reaching 887 MW.
When our second-phase investments are completed by the end of 2027, our total installed capacity is targeted to reach approximately 1200 MW .