[CONSOLIDATION_METHOD_TITLE] [CONSOLIDATION_METHOD]
Related Companies
[]
Related Funds
[]
English
oda_MaterialEventDisclosureGeneralAbstract|
Material Event Disclosure General
oda_UpdateAnnouncementFlag|
Update Notification Flag
Hayır (No)
oda_CorrectionAnnouncementFlag|
Correction Notification Flag
Hayır (No)
oda_DateOfThePreviousNotificationAboutTheSameSubject|
Date Of The Previous Notification About The Same Subject
16.05.2025
oda_DelayedAnnouncementFlag|
Postponed Notification Flag
Hayır (No)
oda_AnnouncementContentSection|
Announcement Content
oda_ExplanationSection|
Explanations
oda_ExplanationTextBlock|
The first part with 19.2 MW installed capacity of Denizli WPP capacity increase project, with a total installed capacity of 24 MW (license number EÜ/3382-10/2050 issued by the Energy Market Regulatory Authority) located in Denizli, of Korda Enerji Üretim Pazarlama İthalat ve İhracat A.Ş., a 100% subsidiary of our company Akfen Yenilenebilir Enerji A.Ş., was provisionally accepted by the Ministry of Energy of the Republic of Türkiye on 22.08.2025 in accordance with the legislation and started commercial energy generation.

Thus, our Company has started to commission the WPP capacity increase investments with a total installed capacity of 102 MW within the scope of the 1st phase investments in accordance with the investment program, and as of 22 August 2025, our Company has reached a total installed power capacity of 802 MW in the renewable energy plants it operates through its subsidiaries.

With the completion of the hybrid solar power plant and wind power plant capacity increase investments within the scope of our company's first phase investments, a capacity of approximately 887 MW will be reached by the end of 2025.


This statement has been translated into English for informational purposes. In the event of any discrepancy between the Turkish and English versions of this disclosure statement, the Turkish version shall prevail.