[CONSOLIDATION_METHOD_TITLE] [CONSOLIDATION_METHOD]
Related Companies
[]
Related Funds
[]
English
oda_MaterialEventDisclosureGeneralAbstract|
Material Event Disclosure General
oda_UpdateAnnouncementFlag|
Update Notification Flag
Hayır (No)
oda_CorrectionAnnouncementFlag|
Correction Notification Flag
Hayır (No)
oda_DateOfThePreviousNotificationAboutTheSameSubject|
Date Of The Previous Notification About The Same Subject
04.09.2025
oda_DelayedAnnouncementFlag|
Postponed Notification Flag
Hayır (No)
oda_AnnouncementContentSection|
Announcement Content
oda_ExplanationSection|
Explanations
oda_ExplanationTextBlock|
- Üçpınar WPP capacity increase project, with an installed capacity of 9.6 MW, (license number EÜ/3433-10/2085 issued by the Energy Market Regulatory Authority) located in Lapseki district of Çanakkale province and owned by Derbent Enerji Üretim Pazarlama İthalat ve İhracat A.Ş., a wholly owned subsidiary of our Company, Akfen Yenilenebilir Enerji A.Ş., and
- Sarıtepe WPP capacity increase project, with an installed capacity of 9.6 MW, (license number EÜ/9381-16/04536  issued by the Energy Market Regulatory Authority), located in Bahçe district of Osmaniye province and owned by İmbat Enerji A.Ş., a wholly owned subsidiary of our company,
have completed the provisional acceptance in compliance with regulations, by the Ministry of Energy of the Republic of Türkiye as of 19.09.2025, and have commenced commercial energy generation.

Thus, wind power plant capacity increase projects, totaling 43.2 MW of installed capacity, within our first phase of investments, have been put into operation. As of September 19, 2025, our Company, through its subsidiaries, has reached a total installed capacity of 828 MW in the renewable energy power plants it operates.

Our company is currently continuing its work to commission the remaining phase 1 investments, consisting of WPP capacity expansion investments, in accordance with its investment program. Upon completion of these WPP capacity expansion investments, our company will reach a capacity of approximately 887 MW by the end of 2025.


This statement has been translated into English for informational purposes. In the event of any discrepancy between the Turkish and English versions of this disclosure statement, the Turkish version shall prevail.