[CONSOLIDATION_METHOD_TITLE] [CONSOLIDATION_METHOD]
Related Companies
[]
Related Funds
[]
English
oda_MaterialEventDisclosureGeneralAbstract|
Material Event Disclosure General
oda_UpdateAnnouncementFlag|
Update Notification Flag
Hayır (No)
oda_CorrectionAnnouncementFlag|
Correction Notification Flag
Hayır (No)
oda_DateOfThePreviousNotificationAboutTheSameSubject|
Date Of The Previous Notification About The Same Subject
03.10.2025
oda_DelayedAnnouncementFlag|
Postponed Notification Flag
Hayır (No)
oda_AnnouncementContentSection|
Announcement Content
oda_ExplanationSection|
Explanations
oda_ExplanationTextBlock|
  • In our announcement dated 03.10.2025 we stated that Hasanoba WPP capacity increase project, with a total installed capacity of 29.5 MW (license number EÜ/3712-3/2262 issued by the Energy Market Regulatory Authority) located in Çanakkale, of Kovancı Enerji Üretim Pazarlama İthalat ve İhracat A.Ş., a 100% subsidiary of our company Akfen Yenilenebilir Enerji A.Ş., had completed the provisional acceptance in compliance with regulations, of its first part with a 17.7 MW installed capacity by the Ministry of Energy of the Republic of Türkiye as of 03.10.2025, and has commenced commercial energy generation.  As of 07.11.2025 the remaining part of this project with 11.8 MW installed capacity has also completed the provisional acceptance and commenced commercial energy generation.

  • Additionally, Kocalar WPP capacity increase project, with a total installed capacity of 29.5 MW (license number EÜ/3570-5/2180 issued by the Energy Market Regulatory Authority) located in Çanakkale, of Isıder Enerji Üretim Pazarlama İthalat ve İhracat A.Ş., a 100% subsidiary of our company Akfen Yenilenebilir Enerji A.Ş., has completed the provisional acceptance in compliance with regulations, of its first part with a 11.8 MW installed capacity by the Ministry of Energy of the Republic of Türkiye as of 07.11.2025, and has commenced commercial energy generation.


Thus, wind power plant capacity increase projects, totaling 84.5 MW of installed capacity, within our first phase of investments, have been put into operation. As of November 7, 2025, our Company, through its subsidiaries, has reached a total installed capacity of 869 MW in the renewable energy power plants it operates.

Our company is currently continuing its work to commission the remaining phase 1 investments, consisting of WPP capacity expansion investments, in accordance with its investment program. Upon completion of these WPP capacity expansion investments, our company will reach a capacity of approximately 887 MW by the end of 2025.


This statement has been translated into English for informational purposes. In the event of any discrepancy between the Turkish and English versions of this disclosure statement, the Turkish version shall prevail.